Permit Application Status

PRBD202201301


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202201301
Building
Finaled
SCHMITT HQ 125 LLC
Alteration/Repair/Replace
Business
Remodeling previously demoed office space.
02/08/2022
04/21/2022
07/30/2023
01/31/2023

Locations

Permits

Permit Number: PRBD202201301

Building
Finaled

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 5/13/2022 (10:00 - 12:00) 5/13/2022 (AM) 05/13/2022
Miscellaneous/Other
Comment Only
05/13/2022
Perimeter wall framing and insulation approved. Interior wall framing approved. Call for separate inspection of new openings in exterior walls when ready.

Progress Inspection Passed 6/27/2022 (12:30 - 2:30) 6/27/2022 (PM) 06/27/2022
Miscellaneous/Other
Comment Only
06/27/2022
Progress inspection of new openings in exterior block wall with steel lintels approved.

Footing Inspection Passed 6/30/2022 (10:00 - 12:00) 6/30/2022 (AM) 06/30/2022
Miscellaneous/Other
Comment Only
06/30/2022
Footings for six stoops with rebar approved.

Progress Inspection Passed 10/7/2022 (2:30 - 3:30) 10/7/2022 (PM) 10/07/2022
Miscellaneous/Other
Comment Only
10/07/2022
Preliminary final inspection with contractor to review accessibility and exiting requirements for a partial final approval. Contractor to schedule other trades and fire prior to building inspection.

Building Final Inspection Partial Pass 10/14/2022 (8:00 - 10:00) 10/14/2022 (AM) 10/14/2022
Miscellaneous/Other
Comment Only
10/14/2022
Partial occupancy approved for employees only to use offices at rear of building and for storage in rear warehouse areas. Public not allowed in any areas.

Fire Inspection Final Partial Pass 10/14/2022 (8:00 - 10:00) 10/14/2022 (AM) 10/18/2022
Building Final Inspection Issue TCO 10/21/2022 (8:00 - 10:00) 10/21/2022 (AM) 10/21/2022
Miscellaneous/Other
Carried Forward
10/21/2022
Still need the final fire, mechanical and plumbing approvals. 30 day temporary occupancy approved.

Fire Inspection Final Not Ready 10/26/2022 (12:30 - 2:30) 10/26/2022 (PM) 10/27/2022
Fire Inspection Final Not Ready 10/24/2022 (8:00 - 10:00) 10/24/2022 (AM) 10/27/2022
Fire Inspection Final Passed 10/28/2022 (AM) 10/31/2022
Building Final Inspection Issue TCO 11/17/2022
Miscellaneous/Other
Carried Forward
11/17/2022
Still need the final fire, mechanical and plumbing approvals. 30 day temporary occupancy approved.

Miscellaneous/Other
Carried Forward
11/17/2022
Extend temporary occupancy 60 days to complete necessary mechanicals.

Miscellaneous/Other
Comment Only
01/13/2023
Extend temporary occupancy 30 days, good until February 13.

Building Final Inspection Passed 1/31/2023 (10:00 - 12:00) 1/31/2023 (AM) 01/31/2023
Miscellaneous/Other
Resolved
01/31/2023
Still need the final fire, mechanical and plumbing approvals. 30 day temporary occupancy approved.

Miscellaneous/Other
Resolved
01/31/2023
Extend temporary occupancy 60 days to complete necessary mechanicals.