Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 5/13/2022 (10:00 - 12:00) | 5/13/2022 (AM) | 05/13/2022 |
Miscellaneous/Other
Comment Only
05/13/2022
Perimeter wall framing and insulation approved. Interior wall framing approved. Call for separate inspection of new openings in exterior walls when ready.
|
||||
Progress Inspection | Passed | 6/27/2022 (12:30 - 2:30) | 6/27/2022 (PM) | 06/27/2022 |
Miscellaneous/Other
Comment Only
06/27/2022
Progress inspection of new openings in exterior block wall with steel lintels approved.
|
||||
Footing Inspection | Passed | 6/30/2022 (10:00 - 12:00) | 6/30/2022 (AM) | 06/30/2022 |
Miscellaneous/Other
Comment Only
06/30/2022
Footings for six stoops with rebar approved.
|
||||
Progress Inspection | Passed | 10/7/2022 (2:30 - 3:30) | 10/7/2022 (PM) | 10/07/2022 |
Miscellaneous/Other
Comment Only
10/07/2022
Preliminary final inspection with contractor to review accessibility and exiting requirements for a partial final approval. Contractor to schedule other trades and fire prior to building inspection.
|
||||
Building Final Inspection | Partial Pass | 10/14/2022 (8:00 - 10:00) | 10/14/2022 (AM) | 10/14/2022 |
Miscellaneous/Other
Comment Only
10/14/2022
Partial occupancy approved for employees only to use offices at rear of building and for storage in rear warehouse areas. Public not allowed in any areas.
|
||||
Fire Inspection Final | Partial Pass | 10/14/2022 (8:00 - 10:00) | 10/14/2022 (AM) | 10/18/2022 |
Building Final Inspection | Issue TCO | 10/21/2022 (8:00 - 10:00) | 10/21/2022 (AM) | 10/21/2022 |
Miscellaneous/Other
Carried Forward
10/21/2022
Still need the final fire, mechanical and plumbing approvals. 30 day temporary occupancy approved.
|
||||
Fire Inspection Final | Not Ready | 10/26/2022 (12:30 - 2:30) | 10/26/2022 (PM) | 10/27/2022 |
Fire Inspection Final | Not Ready | 10/24/2022 (8:00 - 10:00) | 10/24/2022 (AM) | 10/27/2022 |
Fire Inspection Final | Passed | 10/28/2022 (AM) | 10/31/2022 | |
Building Final Inspection | Issue TCO | 11/17/2022 | ||
Miscellaneous/Other
Carried Forward
11/17/2022
Still need the final fire, mechanical and plumbing approvals. 30 day temporary occupancy approved.
|
||||
Miscellaneous/Other
Carried Forward
11/17/2022
Extend temporary occupancy 60 days to complete necessary mechanicals.
|
||||
Miscellaneous/Other
Comment Only
01/13/2023
Extend temporary occupancy 30 days, good until February 13.
|
||||
Building Final Inspection | Passed | 1/31/2023 (10:00 - 12:00) | 1/31/2023 (AM) | 01/31/2023 |
Miscellaneous/Other
Resolved
01/31/2023
Still need the final fire, mechanical and plumbing approvals. 30 day temporary occupancy approved.
|
||||
Miscellaneous/Other
Resolved
01/31/2023
Extend temporary occupancy 60 days to complete necessary mechanicals.
|