Permit Application Status

PRMH202203702


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH202203702
Mechanical/HVAC
Finaled
SCHMITT HQ 125 LLC
Alteration/Repair/Replace
Installing (17) RTUs and associated ductwork, exhaust fans, louvers and others for building renovation.
04/11/2022
05/02/2022
07/25/2023
01/26/2023

Locations

Permits

Permit Number: PRMH202203702

Mechanical
Finaled

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Rough-in Inspection Partial Pass 7/19/2022 (10:00 - 12:00) 7/19/2022 (AM) 07/19/2022
Above Ceiling Inspection Passed 8/25/2022 (8:00 - 10:00) 8/25/2022 (AM) 08/25/2022
Mechanical Final Inspection Partial Pass 9/22/2022 (12:30 - 2:30) 9/22/2022 (PM) 09/23/2022
Mechanical Final Inspection Partial Pass 10/17/2022 (10:00 - 12:00) 10/17/2022 (AM) 10/17/2022
Mechanical Final Inspection Passed 1/26/2023 (10:00 - 12:00) 1/26/2023 (AM) 01/26/2023