Permit Application Status

PRPL202201143


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL202201143
Plumbing
Finaled
SCHMITT HQ 125 LLC
Alteration/Repair/Replace
Plumbing for schmitt music tennant
02/03/2022
02/17/2022
06/07/2023
12/09/2022

Locations

Permits

Permit Number: PRPL202201143

Plumbing
Finaled

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 4/13/2022 (12:30 - 2:30) 4/13/2022 (PM) 04/13/2022
Miscellaneous/Other
Comment Only
04/13/2022
Air tests on 2 groups of under ground plumbing

Plumbing Rough-in Inspection Partial Pass 4/18/2022 (8:00 - 10:00) 4/18/2022 (AM) 04/18/2022
Miscellaneous/Other
Comment Only
04/18/2022
5 lb. Air test on underground bathroom groups on northwest side of building.

Plumbing Rough-in Inspection Partial Pass 4/20/2022 (8:00 - 10:00) 4/20/2022 (AM) 04/20/2022
Miscellaneous/Other
Comment Only
04/20/2022
5 lb. Air test on underground on north bath and branches, 5 lb. Air test on east underground bathrooms, and manometer on flammable waste interceptor. Okay to cover. Will schedule inspection for demo of remaining existing underground.

Plumbing Rough-in Inspection Partial Pass 4/25/2022 (12:30 - 2:30) 4/25/2022 (PM) 04/25/2022
Plumbing Rough-in Inspection Partial Pass 5/10/2022 (8:00 - 10:00) 5/10/2022 (AM) 05/10/2022
Miscellaneous/Other
Comment Only
05/10/2022
All waste and vent air tested on north side. Ok to cover

Plumbing Rough-in Inspection Passed 5/13/2022 (8:00 - 10:00) 5/13/2022 (AM) 05/13/2022
Miscellaneous/Other
Comment Only
05/13/2022
Air test on south side

Plumbing Final Inspection Partial Pass 10/13/2022 (8:00 - 10:00) 10/13/2022 (AM) 10/13/2022
Miscellaneous/Other
Comment Only
10/13/2022
5 manometer tests Visual on mechanical Visual on all fixtures but 2 sinks waiting for counter tops Dap one toilet Fix leak on mixer under lav Repair and test RPZ

Plumbing Final Inspection Passed 12/9/2022 (10:00 - 12:00) 12/9/2022 (AM) 12/09/2022
Miscellaneous/Other
Comment Only
12/09/2022
Sink installations in Steinway room and break room completed. Final final Water heater install too high in ceiling for replacement, maintenance, or emergency without a lift or maybe 12 foot ladder Plumber may not have had a choice as to the elevation of the water heater.