PRBD202300773
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 08/22/2023 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
08/22/2023
Viewed the added wall framing near the store front entry.
Bathrooms framing and blocking also viewed.
Approved
|
||||
| Fire Inspection Final | Partial Pass | 9/8/2023 (8:00 - 10:00) | 9/8/2023 (AM) | 09/08/2023 |
| Bathrooms passed | ||||
| Framing Inspection | Not Ready | 9/8/2023 (7:00 - 8:00) | 9/8/2023 (AM) | 09/08/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/08/2023
No framing to inspect at this time, this is a phased project and work is still ongoing.
|
||||
| Building Final Inspection | Partial Pass | 9/8/2023 (7:00 - 8:00) | 9/8/2023 (AM) | 09/08/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/08/2023
Group bathrooms are approved for use, pending additional signage that is accessibility compliant to be installed at the outside entry of the the group bathrooms.
This can be checked at next inspection.
|
||||
| Framing Inspection | Passed | 9/14/2023 (2:30 - 3:30) | 9/14/2023 (PM) | 09/15/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/14/2023
Rear of store bathrooms... framing and all backing approved
|
||||
| Progress Inspection | Passed | 9/29/2023 (8:00 - 10:00) | 9/29/2023 (AM) | 09/29/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/29/2023
Final approved for the back of store bathrooms. Ok to open for use.
|
||||
| Progress Inspection | Partial Pass | 10/09/2023 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
10/09/2023
AP office walls framing approved, pending electrical inspection prior to covering.
|
||||
| Building Final Inspection | Failed | 12/12/2023 (12:30 - 2:30) | 12/12/2023 (PM) | 12/12/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
12/12/2023
1) All open permits need to be final inspection complete prior to the building final.
2) racking to be anchored as denoted on plans.
3) Environmental Health corrections to be completed and approved by inspector.
|
||||
| Fire Inspection Final | Passed | 12/12/2023 (12:30 - 2:30) | 12/12/2023 (PM) | 12/13/2023 |
| Building Final Inspection | Passed | 4/8/2024 (8:00 - 10:00) | 4/8/2024 (AM) | 04/08/2024 |
|
Corrections:
Miscellaneous/Other
Resolved
04/08/2024
1) All open permits need to be final inspection complete prior to the building final.
2) racking to be anchored as denoted on plans.
3) Environmental Health corrections to be completed and approved by inspector.
|
||||
|
Miscellaneous/Other
Comment Only
04/08/2024
Final for this permit and scope of work... approved
|
||||