Permit Application Status

PRPL202202892


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL202202892
Plumbing
Finaled
CITY OF BLOOMINGTON
Other
Plumbing for new fire station
03/23/2022
04/20/2022
12/13/2023
06/16/2023

Locations

Permits

Permit Number: PRPL202202892

Plumbing
Finaled
04/20/2022
12/13/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 5/27/2022 (8:00 - 10:00) 5/27/2022 (AM) 05/27/2022
Corrections:


Miscellaneous/Other
Comment Only
05/27/2022
Visual on setting and under ground piping for sewage ejector

Plumbing Rough-in Inspection Not Ready 6/15/2022 (12:30 - 2:30) 6/15/2022 (PM) 06/15/2022
Corrections:


Miscellaneous/Other
Carried Forward
06/15/2022
Visual on setting and under ground piping for sewage ejector

Plumbing Rough-in Inspection Partial Pass 6/17/2022 (12:30 - 2:30) 6/17/2022 (PM) 06/17/2022
Corrections:


Miscellaneous/Other
Comment Only
06/17/2022
Air test on all under ground except the sanitary for bathrooms. Sewage ejector Elevator sump Drain tile sump

Plumbing Rough-in Inspection Partial Pass 6/21/2022 (12:30 - 2:30) 6/21/2022 (PM) 06/21/2022
Corrections:


Miscellaneous/Other
Comment Only
06/21/2022
Visual on setting and under ground piping for sewage ejector

Miscellaneous/Other
Comment Only
06/21/2022
Air test on unfortunately bathroom and storm shelter

Plumbing Rough-in Inspection Partial Pass 10/5/2022 (12:30 - 2:30) 10/5/2022 (PM) 10/05/2022
Corrections:


Miscellaneous/Other
Comment Only
10/05/2022
Visual on underground north east corner

Plumbing Rough-in Inspection Partial Pass 10/6/2022 (12:30 - 2:30) 10/6/2022 (PM) 10/06/2022
Corrections:


Miscellaneous/Other
Comment Only
10/06/2022
Visual on underground for flammable waste

Plumbing Rough-in Inspection Partial Pass 10/7/2022 (12:30 - 2:30) 10/7/2022 (PM) 10/07/2022
Corrections:


Miscellaneous/Other
Comment Only
10/07/2022
3 lb air test on 8” and 10” storm main

Plumbing Rough-in Inspection Partial Pass 10/11/2022 (12:30 - 2:30) 10/11/2022 (PM) 10/11/2022
Corrections:


Miscellaneous/Other
Comment Only
10/11/2022
Visual on underground for bathrooms on 1st level west side. Visual on piping for flam tank visual on storm

Plumbing Rough-in Inspection Partial Pass 10/12/2022 (12:30 - 2:30) 10/12/2022 (PM) 10/12/2022
Corrections:


Miscellaneous/Other
Comment Only
10/12/2022
Air test on storm sewer Visual on shower and lav rough-ins. Future air test Visual on installation of flam tank, not piped yet

Plumbing Rough-in Inspection Partial Pass 10/13/2022 (12:30 - 2:30) 10/13/2022 (PM) 10/13/2022
Corrections:


Miscellaneous/Other
Comment Only
10/13/2022
Air test on underground sanitary for bathrooms

Plumbing Rough-in Inspection Partial Pass 10/14/2022 (12:30 - 2:30) 10/14/2022 (PM) 10/14/2022
Corrections:


Miscellaneous/Other
Comment Only
10/14/2022
Tanks buried, underground main facing west.

Plumbing Rough-in Inspection Partial Pass 12/7/2022 (12:30 - 2:30) 12/7/2022 (PM) 12/07/2022
Corrections:


Miscellaneous/Other
Comment Only
12/07/2022
Visual on west set of trench drains Future air test Partial visual on Storm drains Consult with Duke about installation of PRV. Possibly contact the architect.

Plumbing Rough-in Inspection Partial Pass 12/8/2022 (12:30 - 2:30) 12/8/2022 (PM) 12/09/2022
Corrections:


Miscellaneous/Other
Comment Only
12/09/2022
Visual on all under ground for the trench drains. R Ames spoke with the plumbing engineer from EDI, Sandy, who drew the plan. She approved elimination of the PRV valves. Sandy will send change order to architects please email a copy of the change order to R Ames at: rames@bloomingtonmn.gov Thanks Kayla

Plumbing Rough-in Inspection Partial Pass 12/9/2022 (12:30 - 2:30) 12/9/2022 (PM) 12/09/2022
Corrections:


Miscellaneous/Other
Comment Only
12/09/2022
Air test on all piping for trench drains

Plumbing Rough-in Inspection Not Ready 12/12/2022 (12:30 - 2:30) 12/12/2022 (PM) 12/12/2022
Corrections:


Miscellaneous/Other
Comment Only
12/12/2022
Nothing to inspect since Friday. Not necessary

Plumbing Rough-in Inspection Partial Pass 1/27/2023 (12:30 - 2:30) 1/27/2023 (PM) 01/27/2023
Corrections:


Miscellaneous/Other
Comment Only
01/27/2023
Air tests on storm drains. 6 INCH holding 3 PSI Adding restraints and sway bars. Will walk through again when supports are in place

Plumbing Rough-in Inspection Partial Pass 2/2/2023 (12:30 - 2:30) 2/2/2023 (PM) 02/02/2023
Corrections:


Miscellaneous/Other
Comment Only
02/02/2023
Visual on all waste and vent for 2nd level bathrooms and mop sinks on 1st floor. Visual on ice maker boxes and break room sink. Future air test

Plumbing Rough-in Inspection Not Ready 2/8/2023 (10:00 - 12:00) 2/8/2023 (AM) 02/08/2023
2/8: CANCELED and rescheduling for tomorrow. thanks- VM
Plumbing Rough-in Inspection Partial Pass 2/9/2023 (12:30 - 2:30) 2/9/2023 (PM) 02/09/2023
Corrections:


Miscellaneous/Other
Comment Only
02/09/2023
Air test on remaining waste and vent. Storm tests when weather permitting

Plumbing Rough-in Inspection Partial Pass 3/2/2023 (Afternoon) 3/2/2023 (PM) 03/02/2023
Corrections:


Miscellaneous/Other
Comment Only
03/02/2023
Air test on storm water system ok to secure and run

Plumbing Rough-in Inspection Not Ready 3/3/2023 (12:30 - 2:30) 3/3/2023 (PM) 03/03/2023
Corrections:


Miscellaneous/Other
Comment Only
03/02/2023
Air test on storm water system Ok to secure and let run

Plumbing Rough-in Inspection Partial Pass 3/6/2023 (12:30 - 2:30) 3/6/2023 (PM) 03/06/2023
Corrections:


Miscellaneous/Other
Comment Only
03/06/2023
Restraints and hangers on roof drains inspected Mechanical room waste in ceiling inspected

Plumbing Rough-in Inspection Partial Pass 3/24/2023 (10:00 - 12:00) 3/24/2023 (AM) 03/24/2023
Corrections:


Miscellaneous/Other
Comment Only
03/24/2023
Shower pan flood tests

Progress Inspection Partial Pass 6/9/2023 (8:00 - 10:00) 6/9/2023 (AM) 06/09/2023
Corrections:


Miscellaneous/Other
Comment Only
06/09/2023
Manometer test ok. Partial visual finale inspection ok. Need to complete a couple sinks.

Plumbing Final Inspection Passed w/ Conditions 6/15/2023 (2:30 - 3:30) 6/15/2023 (PM) 06/15/2023
Corrections:


Miscellaneous/Other
Comment Only
06/15/2023
Plumbing final inspection ok. Need to install non-potable water tags on South wall outside hose bib and west side roof water hydrant. Also, need to install non potable water stickers at four hose reels in garage.

Plumbing Final Inspection Passed 6/14/2023 (12:30 - 2:30) 06/16/2023
Corrections:


Miscellaneous/Other
Comment Only
06/16/2023
Location: Decontamination Room, serving gear washing machine - RPZ Watts 1-1/2" Model 919QT Serial #28757 Cold Water tested 5/3/23. - RPZ Watts 1-1/2" Model 919QT Serial #28755 Hot Water tested 5/3/23. Location: Janitor Closet,serving truck bay hose reels and west roof hydrant - RPZ Watts 3" Model 957RP Serial UK0038 tested 5/3/23. Location: Sprinkler riser/ water service room, serving irrigation - RPZ Watts 2" Model 919QT Serial #42168 tested 5/3/23.