PRAL201703851
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Acceptance Test Inspection | Failed | 6/29/2017 (7:00 - 8:00) | 6/29/2017 (AM) | 06/29/2017 |
| Need to add device(s) in hallway between main entrance and modified lunch room. Lunch room has both wall mounted and ceiling mounted devices. Rescheduling alarm test for Monday to test all new/relocated devices. | ||||
| Fire Inspection Final | Not Ready | 6/29/2017 (7:00 - 8:00) | 6/29/2017 (AM) | 06/29/2017 |
| Acceptance Test Inspection | Passed | 7/3/2017 | 07/03/2017 | |
| Fire Inspection Final | Passed | 7/3/2017 (7:00 - 8:00) | 7/3/2017 (AM) | 07/03/2017 |
| Fire alarm tested ok. Did not approve a fire final - doors added to lunchroom swing in the wrong direction. lmccarthy 07/03/2017 9:29 AM | ||||