PRAL201708167
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Acceptance Test Inspection | Partial Pass | 11/2/2017 (12:30 - 2:30) | 11/2/2017 | 11/02/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/02/2017
Temp final for fire alarm final for lower level approved.
|
||||
| Acceptance Test Inspection | Partial Pass | 11/13/2017 (Morning) | 11/13/2017 | 11/13/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/13/2017
Fire Final approved for hotel side all floors
Need to test water park and smoke evac.
|
||||
| Acceptance Test Inspection | Partial Pass | 11/15/2017 (Morning) | 11/15/2017 | 11/14/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/14/2017
Fire Alarm Final approved for hotel side guest room floors. Need to retest first floor and need to test waterpark.
Also need to test post fire smoke evac. and generator run test.
|
||||
| Acceptance Test Inspection | Partial Pass | 11/15/2017 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
11/15/2017
Final fire alarm testing approved for hotel and water park.
Need to test smoke evac. and turnstiles once installed and generator run test.
|
||||
| Acceptance Test Inspection | Passed | 11/21/2017 | ||
| Fire Inspection Final | Passed | 11/21/2017 | ||