PRAL201900079
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Acceptance Test Inspection | Passed w/ Conditions | 11/4/2019 (7:00 - 8:00) | 11/4/2019 (AM) | 11/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/04/2019
Need additional notification appliances in/around training room and workout room on 1st floor, north end of building.
Building Maintenance or contractor to call BFD Inspector to inform when work is done.
|
||||
Fire Inspection Final | Passed w/ Conditions | 11/4/2019 (7:00 - 8:00) | 11/4/2019 (AM) | 11/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/04/2019
Need additional notification appliances in/around training room and workout room on 1st floor, north end of building.
Building Maintenance or contractor to call BFD Inspector to inform when work is done.
|