PRBD201700917
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Gypsum Board/Sheet Rock Inspection | Partial Pass | 8/4/2017 (12:30 - 2:30) | 8/4/2017 | 08/04/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/04/2017
Start wall and framing at elevator shaft wall that divides off the mechanical room. Approved to 1st layer. Section at top of shaft to be installed, section is about 3 1/2 " and will be inspected at next inspection.
|
||||
Gypsum Board/Sheet Rock Inspection | Partial Pass | 10/27/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/27/2017
Shaft wall framing at elevator fronts on levels 3,4,5,&6 approved install 1st layer of outer gypsum. Elevator frames are all packed with 1” of core board to maintain rating.
|
||||
Building Final Inspection | Not Ready | 11/28/2017 (8:00 - 10:00) | 11/28/2017 | 11/28/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/28/2017
Progress of parking ramp inspection.... 1) verify removal of handicap parking spot at lower level. 2) ladder access to the parapet roof . This stations and mounted ladder to the roof would kick in the requirement for a guardrail at the highest roof point to bldg. contractor to verify with architect what they like to do , if removal of ladder is an option and any person that accesses this roof has to provide ladder and safety tie off gear.
3) signs for communication to be installed along with the handicap signage at parking stalls. 4) blocking gates needed at the stairs on L1 & 1st level to address handicap cane provision of the code.
|
||||
Fire Inspection Final | Failed | 12/4/2017 (8:00 - 10:00) | 12/4/2017 | 12/04/2017 |
Corrections:
Miscellaneous/Other
Outstanding
12/04/2017
Add exit signs as discussed.
Install stairwell signs as needed.
Need to test emergency call box and area of refuge.
Need mechanical final.
|
||||
Building Final Inspection | Failed | 12/4/2017 (8:00 - 10:00) | 12/4/2017 | 12/04/2017 |
Corrections:
Miscellaneous/Other
Carried Forward
12/04/2017
1) HVAC final needed, detector balancing to be completed. 2) install communication signage in LL. 3) install floor signage in stairways 4) install exit signage at NW stairway at each floor to define stairway exit and on top level of ramp at stair. 5) install gates at LL stairs and NW 1st level for cane detection to comply with accessibility code.
Reinspection of these items are required.
|
||||
Fire Inspection Final | Passed | 12/8/2017 (8:00 - 10:00) | 12/8/2017 | 12/08/2017 |
Building Final Inspection | Passed | 12/8/2017 (8:00 - 10:00) | 12/8/2017 | 12/08/2017 |
Corrections:
Miscellaneous/Other
Resolved
12/08/2017
1) HVAC final needed, detector balancing to be completed. 2) install communication signage in LL. 3) install floor signage in stairways 4) install exit signage at NW stairway at each floor to define stairway exit and on top level of ramp at stair. 5) install gates at LL stairs and NW 1st level for cane detection to comply with accessibility code.
Reinspection of these items are required.
|
||||
Miscellaneous/Other
Comment Only
12/08/2017
All completed... final approved.
|