Summary

PRBD201700986
Building
Finaled
PHD PROPERTIES LLC
New
Residential, multiple family
New construction of 32 unit apartment building (building 2), 4-story with 1 level of underground parking, 40 parking stalls and 32 enclosed bicycle spaces. Palacio Del Sol.
03/01/2017
06/01/2017
01/08/2019

Locations

Permits

Permit Number: PRBD201700986

Building
Finaled
06/01/2017
01/08/2019

Deposits & Bonds

Surety Bond

Item Type Status Original Amount Balance
Surety Bond Security Open $16,000.00 $16,000.00

Surety Bond Details
Type Amount Payment Type Receipt Document # Check Date Invoice Date
Payment $16,000.00 Check 03/01/2017


Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 8/9/2017 (10:00 - 12:00) 8/9/2017 08/09/2017
Corrections:


Miscellaneous/Other
Comment Only
08/09/2017
First layer gypsum in first level walls of trash, elevator, stair walls that can be set. More walls to follow.

Gypsum Board/Sheet Rock Inspection Partial Pass 08/14/2017
Corrections:


Miscellaneous/Other
Comment Only
08/14/2017
First layer on outer side of stair wall approved.

Framing Inspection Partial Pass 8/23/2017 (10:00 - 12:00) 8/23/2017 08/23/2017
Corrections:


Miscellaneous/Other
Comment Only
08/23/2017
2nd floor shaft walls, 1st layer... approved.

Framing Inspection Partial Pass 8/24/2017 (12:30 - 2:30) 8/24/2017 08/24/2017
Corrections:


Miscellaneous/Other
Comment Only
08/24/2017
Under slab probably in the parking garage approved.

Gypsum Board/Sheet Rock Inspection Partial Pass 9/5/2017 (2:30 - 3:30) 9/5/2017 09/05/2017
3rd floor - stair B, both long walls, unit sides, 8 inch OC and perimeters. Stair A, west long wall only, unit side, 8 inch OC and perimeters.
Corrections:


Miscellaneous/Other
Outstanding
09/05/2017
Sheetrock - 1st layer - wood screws, 8 inch OC, perimeter and field. Location 3rd level-Stair B, west and east long walls only. Location 3rd level -stair A, west long wall only. Approved.

Framing Inspection Partial Pass 9/15/2017 (8:00 - 10:00) 9/15/2017 09/15/2017
Corrections:


Miscellaneous/Other
Comment Only
09/15/2017
1st layer of gypsum at outside of stair walls on 4th level... approved to cover with second layer.

Framing Inspection Partial Pass 10/9/2017 (10:00 - 12:00) 10/9/2017 10/09/2017
Corrections:


Miscellaneous/Other
Comment Only
10/09/2017
1) Hallway roof framing needs joist hangers to be added at end of hallway location on each end of hall. 2) elevator shaft framing to be fixed at all levels where the joists were cut out to accommodate the elevator brackets. Also the hoist beam bearing location on 4th floor needs added members under the hoist beam since there is no header to that wall section. The walls are designed to be full bearing members since there is no posts to carry the headers in these wall sections from precast to 3rd floor. Ok to insulate, reinspection of these corrections can be done at the insulation inspection.

Framing Inspection Partial Pass 10/12/2017
Corrections:


Miscellaneous/Other
Comment Only
10/12/2017
Hangers were addded to the joists in hallway of 4th level. The elevator shaft framing is now corrected to provide proper bearing from hoistway all the way down to precast. Insulation approved in the 4th level of elevator shaft and 4th floor hallway ceiling. Approved to cover walls in elevator shaft and ceiling of hallway on 4th floor.

Framing Inspection Partial Pass 10/12/2017
Corrections:


Miscellaneous/Other
Comment Only
10/12/2017
Progress of housewrap on East and north side of building partially approved, drip flashing to be installed over all windows and door openings. To be checked during other progress inspections.

Gypsum Board/Sheet Rock Inspection Partial Pass 10/13/2017 (10:00 - 12:00) 10/13/2017 10/13/2017
Corrections:


Miscellaneous/Other
Comment Only
10/13/2017
4th floor elevator shaft 1st layer of gypsum approved. Ok to install 1st layer on other shafts with inspection to follow prior to installing 2nd layer.

Gypsum Board/Sheet Rock Inspection Partial Pass 10/17/2017 (10:00 - 12:00) 10/17/2017 10/17/2017
Corrections:


Miscellaneous/Other
Comment Only
10/17/2017
4th floor elevator shaft 2nd layer gypsum and north Mechanical shaft 1st layer gypsum approved.

Gypsum Board/Sheet Rock Inspection Not Ready 10/18/2017 (10:00 - 12:00) 10/18/2017 10/18/2017
Corrections:


Miscellaneous/Other
Comment Only
10/18/2017
Contractor called and canceled inspection. Not ready.

Framing Inspection Partial Pass 10/19/2017 (10:00 - 12:00) 10/19/2017 10/19/2017
Corrections:


Miscellaneous/Other
Comment Only
10/19/2017
Approved to spray foam room on fourth floor. Approved to net for insulation ceiling‘s on fourth floor. The first layer gypsum is in progress at Mechanical shafts and at elevator. approvals are marked at each location to allow for second layer covering. Reinspection is ongoing for all shafts.

Framing Inspection Partial Pass 10/20/2017 (10:00 - 12:00) 10/20/2017 10/20/2017
Corrections:


Miscellaneous/Other
Outstanding
10/20/2017
Shafts - all three floors for 3 shafts, and 1 elevator shaft per floor. Note - 2nd layer shafts and elevator shaft must use #8 screws, 2 inch to 2 3/8 inch long W screws per telecom with architect/engineer, spaced 5-7 inch on center per Keegan. NOTE-some 2nd layer has been installed with #6 2 inch screws that need additional #8 screws 2 3/8 inch long. Keegan to mark all 2nd layer installed walls as of today, for 2nd layer screw inspection of 12 areas for three floors.

Framing Inspection Partial Pass 10/23/2017 (12:30 - 2:30) 10/23/2017 10/23/2017
Corrections:


Miscellaneous/Other
Comment Only
10/23/2017
Framing and firestops partial pass, to be reinspected for fridge and washer box gypsum behind each.

Framing Inspection Partial Pass 10/24/2017 (8:00 - 10:00) 10/24/2017 10/24/2017
Corrections:


Miscellaneous/Other
Comment Only
10/24/2017
4th floor unit framing and firestops and gypsum behind washer and fridge Bowes where needed approved. Ok to start insulating walls.

Insulation Inspection Partial Pass 10/25/2017 (10:00 - 12:00) 10/25/2017 10/25/2017
Corrections:


Miscellaneous/Other
Comment Only
10/25/2017
4th floor insulation and poly, approved. Ok to cover.

Framing Inspection Partial Pass 10/26/2017
Corrections:


Miscellaneous/Other
Comment Only
10/26/2017
Framing of rim joist area of 3rd floor. 1) remove drywall screws from angle clip and use proper fasteners. 2) install blocking to top plate along deck posts supports and reinstall structural clips at both end units. 3) squash block to follow the load path, see location marked on wall. Contractor is taking care of these issues ASAP , approved to spray foam rim upon completion of these above listed items.

Framing Inspection Partial Pass 10/30/2017 (8:00 - 10:00) 10/30/2017 10/30/2017
Corrections:


Miscellaneous/Other
Comment Only
10/30/2017
Framing and fire caulking for 3rd floor... painted locations in orange for fire caulk and adding a stud to party wall of both units on north end. Contractor was right behind us correcting issues. A-35 clips used in place of joist hangers at hallway. Contractor to verify with engineer the load values for the location and if this clips are sufficient.

Insulation Inspection Partial Pass 11/1/2017 (10:00 - 12:00) 11/1/2017 11/01/2017
Corrections:


Miscellaneous/Other
Comment Only
11/01/2017
3rd floor insulation approved.

Framing Inspection Partial Pass 11/2/2017 (10:00 - 12:00) 11/2/2017 11/02/2017
Corrections:


Miscellaneous/Other
Comment Only
11/02/2017
Squash blocks and clips at rim framing approved.... ok to spray foam rim.

Framing Inspection Partial Pass 11/3/2017 (12:30 - 2:30) 11/3/2017 11/03/2017
Corrections:


Miscellaneous/Other
Comment Only
11/03/2017
Shear walls on 4th floor, (7” screw pattern) approved.

Fire Rating Inspection Not Ready 11/6/2017 (2:30 - 3:30) 11/6/2017 11/06/2017
Corrections:


Miscellaneous/Other
Comment Only
11/06/2017
Inspection was canceled due to electrical not being ready or inspected and fire stops are also incomplete.

Framing Inspection Failed 11/7/2017 (8:00 - 10:00) 11/7/2017 11/07/2017
Corrections:


Miscellaneous/Other
Comment Only
11/07/2017
Trades inspections to be completed and firestops as well to be completed. Reschedule inspection.

Fire Rating Inspection Passed 11/8/2017 (2:30 - 3:30) 11/8/2017 11/08/2017
Corrections:


Miscellaneous/Other
Outstanding
11/08/2017
Fire caulking approved for second floor except where new sprinkler pipes are going through firewall. Second floor elevator lobby not ready yet.

Fire Rating Inspection Passed 11/9/2017 (7:00 - 8:00) 11/9/2017 11/09/2017
Corrections:


Miscellaneous/Other
Outstanding
11/09/2017
Fireproofing approved where new sprinkler lines where put in OK to insulate ceiling once Fire Marshal gives his approval. On second floor.

Insulation Inspection Partial Pass 11/14/2017 (8:00 - 10:00) 11/14/2017 11/14/2017
Corrections:


Miscellaneous/Other
Comment Only
11/14/2017
Insulation and poly on 2nd floor approved. Ok to also gypsum the upper portions shear walls on 1st level.

Framing Inspection Partial Pass 11/14/2017 (2:30 - 3:30) 11/14/2017 11/14/2017
Corrections:


Miscellaneous/Other
Comment Only
11/14/2017
Shear walls on 3rd floor corrected and approved. Framing at rim on 1st floor approved, ok to spray foam rim.

Framing Inspection Not Ready 11/15/2017 (2:30 - 3:30) 11/15/2017 11/15/2017
Corrections:


Miscellaneous/Other
Comment Only
11/15/2017
Inspection canceled , firestops to be completed.

Framing Inspection Partial Pass 11/16/2017 (2:30 - 3:30) 11/16/2017 11/16/2017
Corrections:


Miscellaneous/Other
Comment Only
11/16/2017
1st floor framing and firestops in units approved, except room 105. Fill cored hole with concrete location at bath plumbing. 4th floor hallway to be firestopped at wiring of lights of the cooridor walls. See UL listing firestop F-B-2050 for firestops at 3&4” pvc piping through floors at elevator lobby/common areas on each floor. These firestops need to be installed per detail.

Framing Inspection Partial Pass 11/20/2017 (8:00 - 10:00) 11/20/2017 11/20/2017
Corrections:


Miscellaneous/Other
Comment Only
11/20/2017
1st layer gypsum at stairs of floors 2&3 approved to cover pending some corrections marked nd viewed by job superintendent.

Insulation Inspection Partial Pass 11/20/2017 (2:30 - 3:30) 11/20/2017 11/20/2017
Corrections:


Miscellaneous/Other
Comment Only
11/20/2017
1st floor insulation and poly at exterior walls approved. Note:PVC piping in commmon area by elevator on 1&2nd floors to be properly firestopped. See Hilti assemblies UL/cUL system NO F-C-7025. And engineering judgement drawing number 216820a. See photos.

Framing Inspection Failed 11/22/2017 (8:00 - 10:00) 11/22/2017 11/22/2017
Corrections:


Miscellaneous/Other
Carried Forward
11/22/2017
Shear walls in 1st floor... drywall sheets need to extend to the bottom plate in order to tie in framing and be a shear wall. Correct issue throughout units.

Progress Inspection Failed 11/22/2017 (2:30 - 3:30) 11/22/2017 11/22/2017
Corrections:


Miscellaneous/Other
Carried Forward
02/05/2018
Shear walls on half the 1st floor units need to be corrected to attach to the bottom wall plate. Cards are marked at the unit entry for the units that passed and can be 2nd layered.

Framing Inspection Partial Pass 11/27/2017 (12:30 - 2:30) 11/27/2017 11/27/2017
Corrections:


Miscellaneous/Other
Resolved
11/27/2017
Shear walls in 1st floor... drywall sheets need to extend to the bottom plate in order to tie in framing and be a shear wall. Correct issue throughout units.

Miscellaneous/Other
Comment Only
11/27/2017
Shear walls on 1st floor corrected and approved to 2nd layer with gypsum.

Miscellaneous/Other
Outstanding
11/27/2017
Tip in walls at all levels to be corrected. Went over the proper way for them to be built and installed with contractor... inspection of these is needed before they can be closed up completely.

Framing Inspection Partial Pass 11/28/2017 (12:30 - 2:30) 11/28/2017 11/28/2017
Corrections:


Miscellaneous/Other
Outstanding
11/28/2017
Tip in walls of the ventilation shafts on 4th, 3rd, & 2nd floors are approved to now 1st layer gypsum at outside of wall.

Framing Inspection Partial Pass 11/29/2017 (10:00 - 12:00) 11/29/2017 11/29/2017
Corrections:


Miscellaneous/Other
Comment Only
11/29/2017
1st floor second layer of shear wallsapproved pending the install of the moisture resistan board at 4 bathrooms that were not completed due to being short on the materials. Contractor to address this ASAP. Framing of drop ceiling and firestops at penetrations approved for 3floor hallway.

Framing Inspection Partial Pass 12/8/2017 (10:00 - 12:00) 12/8/2017 12/08/2017
Corrections:


Miscellaneous/Other
Comment Only
12/08/2017
Mechanical shaft framing approved. Need to re-inspect trash shafts.

Framing Inspection Partial Pass 12/11/2017 (Afternoon) 12/11/2017 12/11/2017
Corrections:


Miscellaneous/Other
Comment Only
12/11/2017
Hallway drop ceiling framing and the fire stops approved... ok to cover.

Framing Inspection Partial Pass 12/26/2017 (8:00 - 10:00) 12/26/2017 12/26/2017
Corrections:


Miscellaneous/Other
Comment Only
12/26/2017
Interior gypsum at trash shaft approved ok to run trash ducting. Note... joint control will have to be addressed when closing up the wall due to the gypsum being over cut at the opening of each tip in wall.

Framing Inspection Partial Pass 01/10/2018
Corrections:


Miscellaneous/Other
Comment Only
01/10/2018
Progress of trash shaft tip in wall to comply with the shaft wall framing... approved. Call for the framing inspection of the tip in wall for each trash chute.

Framing Inspection Partial Pass 1/16/2018 (10:00 - 12:00) 1/16/2018 01/16/2018
Corrections:


Miscellaneous/Other
Outstanding
01/16/2018
Trash shaft tip in panels approved at the inner 2 layers of gypsum. 1) fire caulk around each chute penetration and install the framing to attach the outer layers of gypsum. Framing to also go around the chute opening on all sides.

Gypsum Board/Sheet Rock Inspection Passed 01/25/2018
Corrections:


Miscellaneous/Other
Comment Only
01/25/2018
Fire caulking at trash chute openings floors 1-4 at inside layer of gypsum shaft wall approved. Call for the framing inspection of the fill in shaft wall.

Framing Inspection Partial Pass 1/30/2018 (2:30 - 3:30) 1/30/2018 01/30/2018
Corrections:


Miscellaneous/Other
Comment Only
01/30/2018
Framing of wall at trash chute approved for each level. Went over the front wall of elevator rated wall framing with contractor, call for those framing inspections when ready.

Framing Inspection Partial Pass 2/2/2018 (10:00 - 12:00) 2/2/2018 02/02/2018
Corrections:


Miscellaneous/Other
Comment Only
02/02/2018
Rating of elevator wall front... due to the shaft being out of alignment the framing is butt flush to the inside of the doubled gypsum covering , and 2 layers of gypsum will cover over the framing on the inside and extend over 6 inches onto the surrounding gypsum. The lobby side will be furred out as needed and the gypsum cut back to make sure the joints are staggered. Need to see the layers of gypsum for next inspection at floors 1-4.

Progress Inspection Failed 2/5/2018 (Afternoon) 2/5/2018 02/05/2018
Corrections:


Miscellaneous/Other
Resolved
02/05/2018
Shear walls on half the 1st floor units need to be corrected to attach to the bottom wall plate. Cards are marked at the unit entry for the units that passed and can be 2nd layered.

Miscellaneous/Other
Carried Forward
02/08/2018
Gypsum at elevator lobby side is pending the fire caulking around the membrane penetration and the staggering of the drywall joints. Call for reinspection of this covering.

Progress Inspection Failed 2/9/2018 (8:00 - 10:00) 2/9/2018 02/09/2018
Corrections:


Miscellaneous/Other
Resolved
02/09/2018
Gypsum at elevator lobby side is pending the fire caulking around the membrane penetration and the staggering of the drywall joints. Call for reinspection of this covering.

Miscellaneous/Other
Outstanding
02/09/2018
Interior of elevator shaft front wall has the upper corner of the wall on 4th that needs to be covered with gypsum and the joints staggered. Each floor at the bottom of door for each side side of rails, the openings also have to be covered with gypsum. The gypsum at 3rd floor needs to be fastened.

Framing Inspection Partial Pass 2/16/2018 (10:00 - 12:00) 2/16/2018 02/16/2018
Corrections:


Miscellaneous/Other
Comment Only
02/16/2018
Viewed firestops in garage, the main area is completed, but the adjoining rooms have some that need to be installed. Reinspection needed.

Progress Inspection Not Ready 2/23/2018 (10:00 - 12:00) 2/23/2018 02/23/2018
Corrections:


Miscellaneous/Other
Comment Only
02/23/2018
Progress of job, work is still ongoing. Went over conditions and requirements for future inspections and temp CO. Call for progress inspection, trades inspections, as needed.

Progress Inspection Not Ready 03/09/2018
Progress: 1) at 2nd and 3rd floor closet room by stair”A” there are 3 penetrations that need to be fire stopped and gypsum patched above the ceiling at the shaft and floor rating. 2) signage at elevator needs to have brail for each level. 3) the opening of masonry wall in electrical room in parking level to be firestopped to wall rating of 1 hour. Sprinkler pipe to be firestopped at through floor...and the condensate pipe and water line wrapped in armaflex to also be firestopped at garage ceiling. 4) correct handrail leading from 1st floor to lower level. 5) complete exterior work, and the grading at front entry... install a temp step and walkway to stair B exit. 6) complete misc work that is still ongoing.
Corrections:


Miscellaneous/Other
Outstanding
03/09/2018
Progress:1) 2nd and 3rd floors in the closer by the elevator above ceiling... patch gypsum at rated floor assembly and firecaulk the penetrations that go through floor and shaft. 2) signage at elevator for each floor to have brail . 3) firestop the penetrations through the 1 hour rated wall of electrical room in parking level. 4) firestop at sprinkler piping through floor of parking level trash room... also firestop the condensate pipe and the armaflex covered water pipe , both in parking garage. 5) complete the grading at front entry, the ramp to comply with accessibility code. 6) complete all exterior overhead work and other misc work... install temp steps and walkway for exiting outside of stair B exit. 7) correct handrail that leads from 1st level to parking in lower level at stair A.

Fire Inspection Final Passed 3/14/2018 (12:30 - 2:30) 3/14/2018 03/14/2018
Building Final Inspection Partial Pass 3/14/2018 (12:30 - 2:30) 3/14/2018 03/14/2018
Corrections:


Miscellaneous/Other
Resolved
03/15/2018
Unit 101, accessibility requirements.... hood vent operation is out of the reach range. 1) Run control to the switch that is in place for the hood vent control. 2) install towel hook or towel bar within 48” reach range at the accessible bathroom. Lower decks at units 103 & 105 have temp guards installed till the work at pool and grade is to be done... close up the infill openings to 4” max opening width. Temp Exit stair outside of stair “B” close up the railing infills to 4” max and install a temp handrail. Install accessible parking signage at the below grade parking garage handicap stall.

Miscellaneous/Other
Comment Only
03/14/2018
Approved for temp occupancy of the building pending the corrections marked as “outstanding “ from this inspection.

Building Final Inspection Partial Pass 03/15/2018
Corrections:


Miscellaneous/Other
Comment Only
03/15/2018
The outstanding corrections from inspection on3/14/18 are corrected. Occupancy of building approved. See the outstanding correction with the front entry parking and accessibility.

Miscellaneous/Other
Outstanding
03/15/2018
The 2 accessibility parking spots at the front entry to be corrected... signage to be installed 60-66” from grade to the bottom of signs and centered at the 2 stalls. The access route to also be marked “no parking” . What is in place does not comply with the accessibility code. This issue to be corrected as soon as possible.

Lighting Inspection Passed 04/06/2018
Inspected 4/3
Framing Inspection Passed 05/16/2018
Corrections:


Miscellaneous/Other
Comment Only
05/16/2018
Rebar inspection for the pool... bar is installed as per plans. Approved to install shot Crete.

Building Final Inspection Partial Pass 7/3/2018 (12:30 - 2:30) 7/3/2018 07/03/2018
Corrections:


Miscellaneous/Other
Comment Only
07/03/2018
Final for this permit is pending final inspection of pool heater .... permit MH201703976. Electrical for pool heater, permit EL201712149. Driveway permit, 201804663. 1) Install exit sign on pool gate at inside of fence that leads to the public way sidewalk. 2) Due to the striping of parking lot, the new layout will be compliant with the signs installed at the building columns. Removed the sign on the bollard to avoid confusion with the adjoining non-accessible parking space. 3) Provide asbuilt to utilities . Complete all the above items, and call for final inspections. 952-563-8930

Building Final Inspection Passed 07/12/2018
Corrections:


Miscellaneous/Other
Comment Only
07/12/2018
All work and inspections are completed and signed off. Permit 201703976 is approved for final with the final inspection being done on 7/11/18. All misc. corrections are completed. Pool has been signed off by the state, Bloomington EH. Dept. now takes over with inspections. Final for this permit is approved.