Summary

PRBD201701029
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Build-out for Villa Pizza tenant. (Separate permit issued prior for framing only and restrooms.)
03/01/2017
03/17/2017
01/29/2026
06/16/2017

Locations

Permits

Permit Number: PRBD201701029

Building
Finaled
03/17/2017
01/29/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 3/29/2017 (8:00 - 10:00) 3/29/2017 03/29/2017
Corrections:


Miscellaneous/Other
Comment Only
03/29/2017
Walls, bulkhead, ok to cover. Leave open chase with piping for firestops inspection. Fireproofing to be patched as needed.

Framing Inspection Partial Pass 4/6/2017 (10:00 - 12:00) 4/6/2017 04/06/2017
Corrections:


Miscellaneous/Other
Comment Only
04/06/2017
Framing at front ceiling approved, pending electrical inspection.

Framing Inspection Failed 4/13/2017 (8:00 - 10:00) 4/13/2017 04/14/2017
Corrections:


Miscellaneous/Other
Inspection is canceled, not ready

Framing Inspection Passed 4/19/2017 (10:00 - 12:00) 4/19/2017 04/19/2017
Corrections:


Miscellaneous/Other
Comment Only
04/19/2017
Ceiling framing by hoods approved, access panel to be installed on right side of hood ceiling for access to electrical.

Fire Rating Inspection Partial Pass 4/25/2017 (10:00 - 12:00) 4/25/2017 04/25/2017
Corrections:


Miscellaneous/Other
Comment Only
04/25/2017
Viewed firestop at grease duct on 1st floor of the bottom side of the assembly. Ceilings can be covered pending fire sprinkler inspection is completed. Firestops at each level are to be inspected when completed, contractor has sent pictures of the steps to inspector for step verification.

Fire Rating Inspection Partial Pass 4/27/2017 (12:30 - 2:30) 4/27/2017 04/27/2017
Corrections:


Miscellaneous/Other
Comment Only
04/27/2017
Viewed firestops at grease duct on 4th, 3rd, floors. 2nd floor and through wall on 1st to be inspected.

Fire Inspection Final Failed 4/28/2017 (12:30 - 2:30) 4/28/2017 04/28/2017
Need to close out all life safety related permits. Need to verify kitchen hood's gas valve is installed per listing.
Fire Inspection Final Issue TCO 04/28/2017
Ok to stock, train, and cook. E/M lights approved
Building Final Inspection Partial Pass 4/28/2017 (12:30 - 2:30) 4/28/2017 04/28/2017
Corrections:


Miscellaneous/Other
Comment Only
04/28/2017
Veiwed fire stop for grease duct on second floor at storage in women's bathroom... approved. Grease duct that runs through wall of exit passageway and into Erie of women's bathroom above ceiling to be completed with gypsum and firestopped. Temp for training and stock is approved pending the passageway firestop at grease duct. Reinspection to be set up first of next week to view this, (May1st).

Fire Rating Inspection Partial Pass 05/02/2017
Corrections:


Miscellaneous/Other
Comment Only
05/02/2017
Firestop at grease duct through wall on 2nd floor at both sides of exit passageway wall approved. Note: grease duct in stairwell of 4th floor needs a 2hour wall built to remove/relocate it out of the stairway. Issues include:sprinkler relocation and layout, access for two electrical boxes, access to a ball valve shutoff, and maintaining opening for stair pressureization. Acccess panels will need to be installed in this shaft enclosure for duct access cleaning.

Fire Rating Inspection Partial Pass 5/3/2017 (8:00 - 10:00) 5/3/2017 05/03/2017
Corrections:


Miscellaneous/Other
Comment Only
05/03/2017
2nd floor firestop approved at both sides of grease duct.

Fire Rating Inspection Partial Pass 05/05/2017
Corrections:


Miscellaneous/Other
Comment Only
05/05/2017
Approval for temp occupancy to open, with a 30 day extension from this date to install the 2hr rated walls to remove duct from 4th floor stair. E.H. Follow up with their corrections per E.H. Inspector.

Fire Rating Inspection Partial Pass 05/17/2017
Corrections:


Miscellaneous/Other
Comment Only
05/17/2017
Framing and building of shaft wall assembly to enclose the grease duct, and relocate the rated walls of the 4th floor stairway. The framing and gypsum layers are viewed in different stages due to complexity of how this enclosure has to be built. As of 5/17/17 the center wall framing, and open shaft framing for stair pressurization is approved. Remaining ceiling and wall framing to be inspected.

Fire Rating Inspection Partial Pass 05/22/2017
Corrections:


Miscellaneous/Other
Comment Only
05/22/2017
F6 stair shaft framing for grease duct enclosure and redefinement of the rated stair walls. Shaft framing is ongoing and C.O.B inspector has stopped in to view framing progress ar each phase. Also viewed pictures contractor took at each phase of construction. The shaft wall framing and 2 layer gypsum outer layer is compliant for a 2 hour rating. The 2 access panel doors are yet to be installed and fireproofing to be patched-in around the grease duct at the beams on 2nd & 3rd floor.

Fire Rating Inspection Passed 05/30/2017
Corrections:


Miscellaneous/Other
Comment Only
05/30/2017
All fireproofing at the beams where the grease duct abuts is now patched. The shaft in stair f6 is completed. The wall enclosure for the stairway f6 now follows the shaft wall framing for redefining the stair enclosure. All is approved for building final

Building Final Inspection Passed 05/30/2017
Corrections:


Miscellaneous/Other
Comment Only
05/30/2017
All work is completed and conditions for occupancy have been met and completed.

Fire Inspection Final Passed 06/16/2017
Corrections:


Miscellaneous/Other
Comment Only
06/16/2017
See associated sprinkler and alarm permits. Final was given on those permits.