PRBD201701031
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
08/28/2017
Need to test stairwell door release once installed.
|
||||
Framing Inspection | Partial Pass | 3/31/2017 (8:00 - 10:00) | 3/31/2017 | 03/31/2017 |
Corrections:
Miscellaneous/Other
Comment Only
03/31/2017
Ok to cover bathrooms and elevator lobby at 4th&5th floors. Will re inspect later this morning the firestops being stuffed with mineral wool at bathrooms on both floors.
|
||||
Framing Inspection | Passed | 7/14/2017 (8:00 - 10:00) | 7/14/2017 | 07/14/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/14/2017
Framing was approved with inspections with associated permit.
|
||||
Building Final Inspection | Passed w/ Conditions | 8/28/2017 (8:00 - 10:00) | 8/28/2017 | 08/28/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/28/2017
Final approved, pending fire reinspection of the 5th floor door.
|
||||
Fire Inspection Final | Not Ready | 8/28/2017 (8:00 - 10:00) | 8/28/2017 | 08/28/2017 |
Corrections:
Miscellaneous/Other
Carried Forward
08/28/2017
Need to test stairwell door release once installed.
|