PRBD201701738
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 4/28/2017 (10:00 - 12:00) | 4/28/2017 | 04/28/2017 |
Corrections:
Miscellaneous/Other
Outstanding
04/28/2017
Wall framing and fire stops in walls approved on fourth floor. OK to cover
|
||||
Framing Inspection | Partial Pass | 5/9/2017 (10:00 - 12:00) | 5/9/2017 | 05/09/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/09/2017
5th floor wall framing approved to cover. Verbal to contractor to add nail plates to four studs in bathroom where PVC pipe thing runs through studs.
|
||||
Framing Inspection | Passed | 7/14/2017 (8:00 - 10:00) | 7/14/2017 | 07/14/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/14/2017
Framing was approved with prior inspection, misc items associated with it were corrected. Inspection today was a walk through for progress and issues that need to be addressed for temp CO or final.
|
||||
Fire Inspection Final | Passed | 7/20/2017 (8:00 - 10:00) | 7/20/2017 | 07/20/2017 |
Building Final Inspection | Passed w/ Conditions | 7/20/2017 (8:00 - 10:00) | 7/20/2017 | 07/20/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/20/2017
Plumbing permit finaled, dishwashers are not installed but are roughed in and plumbing inspector was fine to final out permit. Training room does not have occupant load of more than 50, signage not needed. Exiting approved. Minor cleanup and finishing of finishes to be completed and installed. Final for C. of O. Approved.
|