Permit Application Status

PRBD201701868


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201701868
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Interior remodel for The Escape Game at MOA.
03/28/2017
04/11/2017
03/10/2025

Locations

Permits

Permit Number: PRBD201701868

Building
Finaled
04/11/2017
03/10/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Partial Pass 4/18/2017 (8:00 - 10:00) 4/18/2017 04/18/2017
Corrections:


Miscellaneous/Other
Comment Only
04/18/2017
Ok to cover store front walls, no electrical in walls.

Framing Inspection Partial Pass 4/26/2017 (12:30 - 2:30) 4/26/2017 04/26/2017
Corrections:


Miscellaneous/Other
Comment Only
04/26/2017
Ok to one side cover rooms: jail cells, gallery and gallery rooms. Consult with opening of cabinets at hidden closet at to comply with width clearance as per the door opening (curator office).

Framing Inspection Partial Pass 5/1/2017 (8:00 - 10:00) 5/1/2017 05/01/2017
Corrections:


Miscellaneous/Other
Comment Only
05/01/2017
Approved to cover walls only. Conversation with general contractor as to where accessibility requirements pertain to this project.

Framing Inspection Partial Pass 5/8/2017 (10:00 - 12:00) 5/8/2017 05/08/2017
Corrections:


Miscellaneous/Other
Comment Only
05/08/2017
Ok to cover ceilings in rooms other than: cabin, goldmine,& curator 1&2 rooms ... leave those open for sprinkler inspection. Two door openings to be readjusted for 18" pull per accessibility, rooms: bridge#117 & 124.

Building Final Inspection Partial Pass 5/26/2017 (8:00 - 10:00) 5/26/2017 05/26/2017
Corrections:


Miscellaneous/Other
Comment Only
05/26/2017
Progress of work at this space... fire inspection has to follow up with their final , and a temp to occupy will be given when completion of work is ready and inspected by C.O.B .

Fire Inspection Final Not Ready 5/26/2017 (8:00 - 10:00) 5/26/2017 05/26/2017
Corrections:


Miscellaneous/Other
Comment Only
05/26/2017
Discussed with general contractor on final requirements. Need to test door release.

Building Final Inspection Partial Pass 6/8/2017 (8:00 - 10:00) 6/8/2017 06/08/2017
Temp CO
Corrections:


Miscellaneous/Other
Comment Only
06/08/2017
Log cabin game: guard rail and hand rail to meet code requirements. No more tha 4 inches of opening at guard and handrail to be lowered to within the code requirements. Approved to train at games not including to rear 2 games ( mars and the unnamed game).

Fire Inspection Final Failed 06/14/2017
Corrections:


Miscellaneous/Other
Outstanding
06/15/2017
canopy and wall foliage decoration in cabin room shall be removed or provide documentation of products flame spread/smoke develop index for Fire Marshal Approval

Building Final Inspection Partial Pass 6/22/2017 (8:00 - 10:00) 6/22/2017 06/22/2017
Corrections:


Miscellaneous/Other
Comment Only
06/22/2017
Temp C.O. Approved for public opening. The last to games are not online for use yet. They are not accessed for public use. The 1 game will need a new permit for buildout when the decision is made on the type of game going in.

Fire Inspection Final Passed w/ Conditions 6/22/2017 (8:00 - 10:00) 6/22/2017 06/22/2017
Corrections:


Miscellaneous/Other
Comment Only
06/22/2017
Passed with condition of tenant contacting Fire Marshal Office when final game room is built out and prior occupancy for general public

Building Final Inspection Not Ready 7/28/2017 (10:00 - 12:00) 7/28/2017 07/28/2017
Corrections:


Miscellaneous/Other
Comment Only
07/28/2017
Inspection canceled

Fire Inspection Final Not Ready 7/28/2017 (10:00 - 12:00) 7/28/2017 07/28/2017
Corrections:


Miscellaneous/Other
Resolved
07/28/2017
Fire alarm final failed. Sprinkler permit final failed (need to relocated heads under large duct work) Install exit signs per COB approved plan. Install fire extinguishers as discussed. Install fire exit hardware as needed and exit doors leading to exit passageway shall be smoke gasketed, fully close and latch. Install occupancy load sign.

Fire Inspection Final Passed 8/1/2017 (8:00 - 10:00) 8/1/2017 08/01/2017
Corrections:


Miscellaneous/Other
Resolved
08/01/2017
Fire alarm final failed. Sprinkler permit final failed (need to relocated heads under large duct work) Install exit signs per COB approved plan. Install fire extinguishers as discussed. Install fire exit hardware as needed and exit doors leading to exit passageway shall be smoke gasketed, fully close and latch. Install occupancy load sign.

Building Final Inspection Passed 8/1/2017 (8:00 - 10:00) 8/1/2017 08/01/2017
Contractor wanted CO paperwork so had to manually change status to final since system didn't do it after all inspections cleared. ajacobson 11/30/2017 9:09 AM
Corrections:


Miscellaneous/Other
Comment Only
08/01/2017
Final approved for all this buildout, the last game has been themed and all work is completed. Approved for public use with all games.