PRBD201701872
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 5/3/2017 (10:00 - 12:00) | 5/3/2017 | 05/03/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/03/2017
Phase 1: wall framing approved to cover. See plan for phasing.
|
||||
Framing Inspection | Partial Pass | 05/23/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/23/2017
2 infill walll sections, ok to cover.
|
||||
Framing Inspection | Partial Pass | 5/31/2017 (8:00 - 10:00) | 5/31/2017 | 05/31/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/31/2017
40 ft wall approved to cover
|
||||
Framing Inspection | Passed | 06/14/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/14/2017
Phase 3 .... 10 ft. Of interior wall partition, approved to cover.
|
||||
Building Final Inspection | Failed | 6/27/2017 (8:00 - 10:00) | 6/27/2017 | 06/27/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/27/2017
1) install exit light over 2nd door opening in meeting room. 2) install occupancy load signage to meeting room (occ-72) per plans.
|
||||
Building Final Inspection | Passed | 8/15/2017 (10:00 - 12:00) | 8/15/2017 | 08/15/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/15/2017
Final approved .
|