PRBD201702504
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 5/25/2017 (8:00 - 10:00) | 5/25/2017 | 05/25/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/25/2017
Wall is a partition wall that attaches to the structural members of the floor above. Fireproofing needs to be patched in at all the track attachment points. Abandoned sprinkler head needs to be addressed for coverage or abandonment. Wall framing is completely covered and finished, FRP is installed at kitchen side of wall. Due to this being a partition wall only C.O.B. Will not make contractor remove covering.
|
||||
Framing Inspection | Passed | 5/26/2017 (10:00 - 12:00) | 5/26/2017 | 05/26/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/26/2017
Fire sprinkler corrected and inspected. Fire proofing patched as needed to match existing.
|
||||
Fire Inspection Final | Passed | 5/26/2017 (10:00 - 12:00) | 5/26/2017 | 05/26/2017 |
Building Final Inspection | Failed | 5/26/2017 (10:00 - 12:00) | 5/26/2017 | 05/26/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/26/2017
Install smoke seal at rear door... clean space and complete minor patching. ok to stock and train and setup. Final inspection needed.
|
||||
Building Final Inspection | Passed w/ Conditions | 6/8/2017 (8:00 - 10:00) | 6/8/2017 | 06/08/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/08/2017
Final CO approved to open to public, pending follow up withE.H. For minor issues.
|