PRBD201702606
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 5/18/2017 (10:00 - 12:00) | 5/18/2017 | 05/18/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/18/2017
Wall framing approved to cover, excluding storefront and at columns. Storefront and columns need to be reinspection, fireproofing needed at all columns and beams.
|
||||
Framing Inspection | Failed | 5/24/2017 (10:00 - 12:00) | 5/24/2017 | 05/24/2017 |
partial framing | ||||
Corrections:
Miscellaneous/Other
Comment Only
05/24/2017
Ceiling framing and columns can not be covered at this time, till fireproofing has been patched and inspected. Fire sprinklers and electrical to also be inspected. provide opening for smoke Evac in front plenum ceiling. Reinspection needed.
|
||||
Framing Inspection | Passed | 5/26/2017 (10:00 - 12:00) | 5/26/2017 | 05/26/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/26/2017
Remaining roaming approved to cover. Note: plenum opening of 12"x12" minimum, to be installed in the closed off ceiling at storefront... to be checked at final.
|
||||
Progress Inspection | Passed | 6/19/2017 (10:00 - 12:00) | 6/19/2017 | 06/19/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/19/2017
Pending electrical approval, ok to cover with drop in ceiling panels.
|
||||
Building Final Inspection | Passed w/ Conditions | 6/26/2017 (12:30 - 2:30) | 6/26/2017 | 06/26/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/26/2017
1)install smoke seal to rear door and adjust to close and latch. Fire inspector to follow up... approved for building final, pending fire inspector follow up.
|
||||
Fire Inspection Final | Failed | 6/26/2017 (12:30 - 2:30) | 6/26/2017 | 06/26/2017 |
Corrections:
Doors not self-closing and latching.
Carried Forward
06/26/2017
Rear exit passageway door not self-closing and latching.
|
||||
Fire Inspection Final | Passed w/ Conditions | 6/27/2017 (12:30 - 2:30) | 6/27/2017 | 06/27/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/27/2017
Ensure rear door latches. Contractor on site and adjusting as needed.
|
||||
Fire Inspection Final | VOID | 10/13/2017 | ||
Corrections:
Doors not self-closing and latching.
Outstanding
06/26/2017
Rear exit passageway door not self-closing and latching.
|