Permit Application Status

PRBD201702906


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201702906
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
ASICS (138 North Garden) - tenant remodel of existing retail space in the MOA for new ASICS store.
04/24/2017
05/12/2017
04/21/2021
08/16/2017

Locations

Permits

Permit Number: PRBD201702906

Building
Finaled
05/12/2017
04/21/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 5/26/2017 (8:00 - 10:00) 5/26/2017 05/26/2017
Corrections:


Miscellaneous/Other
Comment Only
05/26/2017
Patch fireproofing at column and center beam. Holes in floor above to be properly firestopped, and fix holes in ceiling/floor for firestop of 2 hour rating. Ok to one side back walls.

Framing Inspection Partial Pass 6/7/2017 (8:00 - 10:00) 6/7/2017 06/07/2017
Corrections:


Miscellaneous/Other
Comment Only
06/07/2017
All walls only approved to cover. Sprinkler inspection needed, call in for setup and also schedule framing for ceilings.

Framing Inspection Partial Pass 6/8/2017 (Morning) 6/8/2017 06/08/2017
Corrections:


Miscellaneous/Other
Comment Only
06/08/2017
Approved to cover store front and ceiling in small room. Call for framing of the ceiling in main area.

Framing Inspection Passed 6/14/2017 (8:00 - 10:00) 6/14/2017 06/14/2017
Corrections:


Miscellaneous/Other
Comment Only
06/14/2017
Main area ceiling framing and above ceiling approved to cover. Plenum openings are free and clear to the smoke evac system.

Building Final Inspection Partial Pass 8/8/2017 (8:00 - 10:00) 8/8/2017 08/08/2017
Corrections:


Miscellaneous/Other
Comment Only
08/08/2017
1) fitting room bench to be accessibility compliant,( the installed bench is to small). 2) patch at exit passageway wall where piping was removed. 3) Set up store to view egress path. Approved to stock and train.

Fire Inspection Final Passed 8/8/2017 (8:00 - 10:00) 8/8/2017 08/08/2017
Building Final Inspection Passed 8/16/2017 (10:00 - 12:00) 8/16/2017 08/16/2017
Corrections:


Miscellaneous/Other
Comment Only
08/16/2017
Final approval for C.O. Approved, opening to public , approved.