PRBD201703185
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 5/23/2017 (10:00 - 12:00) | 5/23/2017 | 05/23/2017 |
check in at front desk | ||||
Corrections:
Miscellaneous/Other
Comment Only
05/23/2017
Framing approved contingent on electrical rough in approval.
|
||||
Fire Inspection Final | Passed | 6/7/2017 (10:00 - 12:00) | 6/7/2017 | 06/07/2017 |
Building Final Inspection | Passed | 6/7/2017 (10:00 - 12:00) | 6/7/2017 | 06/07/2017 |