PRBD201703349
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Not Ready | 7/21/2017 (8:00 - 10:00) | 7/21/2017 | 07/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/21/2017
Framing consultation for dismissing wall framing around the bar joist beam. C.O.B. is ok with boxing in beam and wall with sliptrack built under. This change does need to be approved with architect and verified at inspection.
|
||||
Footing Inspection | Passed w/ Conditions | 8/21/2017 (12:30 - 2:30) | 8/21/2017 | 08/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/21/2017
Footing and foundation wall is already poured and in place. Contractor took pictures of footing rebar. The plans do not show any detail for this section view or how this was installed. Contractor to have approval from engineer/architect for this installation.
|
||||
Framing Inspection | Failed | 8/22/2017 (10:00 - 12:00) | 8/22/2017 | 08/22/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/22/2017
Rescinding previous "approval with conditions" for the footing inspection dated 8/21/17. Engineer /architect to provide new documentation of the footing and foundation wall install that was not done to detail as what is on the plans. New detail and design needed to move forward with inspections for the ramp.
|
||||
Framing Inspection | Partial Pass | 8/25/2017 (8:00 - 10:00) | 08/22/2017 | |
Corrections:
Miscellaneous/Other
Comment Only
08/22/2017
Interior framing at FedEx, above ceiling of the one side to encompass truss at diving wall between spaces. (See plan addendum.) approved to cover. Opposite side of wall and the wall infill to be inspected when ready.
|
||||
Framing Inspection | Passed w/ Conditions | 8/25/2017 (8:00 - 10:00) | 8/25/2017 | 08/25/2017 |
Corrections:
Miscellaneous/Other
Outstanding
08/25/2017
Framing - A) above ceiling, dimising wall to reduce existing FedEx space.B) call for above ceiling for electrical, low voltage, and fire sprinkler.
|
||||
Framing Inspection | Passed | 9/13/2017 (10:00 - 12:00) | 9/13/2017 | 09/13/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/13/2017
Approved framing on opposing side of dividing wall. Ok to cover.
|
||||
Fire Inspection Final | Failed | 10/9/2017 (10:00 - 12:00) | 10/9/2017 | 10/09/2017 |
Building Final Inspection | Failed | 10/9/2017 (10:00 - 12:00) | 10/9/2017 | 10/09/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/09/2017
Electrical final and fire marshal final needed. 1) Install guard at ramp around electrical panel bank. 2) install railing at ramp. 3) correct spacing of sprinkler heads and diffusers in building space.
|
||||
Fire Inspection Final | Passed | 10/10/2017 (8:00 - 10:00) | 10/10/2017 | 10/10/2017 |
Building Final Inspection | Passed | 11/17/2017 (10:00 - 12:00) | 11/17/2017 | 11/17/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/17/2017
All inspections completed, all work completed. Final approved
|