PRBD201703354
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 6/8/2017 (10:00 - 12:00) | 6/8/2017 | 06/08/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/08/2017
Extension to wall in both men's and women's bathrooms approved. No covering till electrical is inspected. One outlet is relocated to each bathroom.
|
||||
Progress Inspection | Partial Pass | 6/19/2017 (8:00 - 10:00) | 6/19/2017 | 06/19/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/19/2017
Framing and blocking of family bathroom... approved phase1 bathroom group on south second level.
|
||||
Building Final Inspection | Partial Pass | 7/14/2017 (10:00 - 12:00) | 7/14/2017 | 07/14/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/14/2017
Phase 1 of permit ( first floor bathrooms .... men, women's, and family) approved for public use.
|
||||
Progress Inspection | Partial Pass | 7/21/2017 (10:00 - 12:00) | 7/21/2017 | 07/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/21/2017
Framing existing.... blocking installed for grab bars and others attached apparatus. Market hall bathrooms off loading dock entry.
|
||||
Fire Inspection Final | Not Ready | 8/9/2017 (12:30 - 2:30) | 8/9/2017 | 08/09/2017 |
Corrections:
Smoke alarm placement
Carried Forward
08/09/2017
Smoke alarm placement. Smokes not installed per their listing.
|
||||
Building Final Inspection | Passed | 8/10/2017 (10:00 - 12:00) | 8/10/2017 | 08/10/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/10/2017
Phase 2 bathrooms approved for public use. This is the full final for this permit.
|
||||
Fire Inspection Final | Passed | 8/10/2017 (10:00 - 12:00) | 8/10/2017 | 08/10/2017 |
Corrections:
Smoke alarm placement
Outstanding
08/09/2017
Smoke alarm placement. Smokes not installed per their listing.
|