Permit Application Status

PRBD201703863


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201703863
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Assembly, theater, symphony hall
Interior alterations to existing theater complex with mezzanine. Cinemax (CMX Cinema) - Mall of America. Scope to include alterations to entry storefront, new platform framing and lounge seating in auditoriums, enlarging the lobby concessions and adding a new sports bar and lounge, relocating the commercial kitchen, providing several food station areas, and adding 2 offices and a breakroom at the end of the west common corridor.
05/17/2017
08/28/2017
10/23/2018
04/26/2018

Locations

Permits

Permit Number: PRBD201703863

Building
Finaled
08/28/2017
10/23/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 08/29/2017
Corrections:


Miscellaneous/Other
Comment Only
08/29/2017
Infill wall framing and halfwall framing, gypsum board first layer at rated wall af the theaters to the right of main entry. Approved to cover.

Progress Inspection Partial Pass 10/11/2017 (10:00 - 12:00) 10/11/2017 10/11/2017
Corrections:


Miscellaneous/Other
Comment Only
10/11/2017
Above ceiling inspection in theaters 1,2,3 approved pending electrical inspection and fire inspection for theater 3 in the back exit corridor.

Fire Rough-in Inspection VOID 10/11/2017 (10:00 - 12:00) 10/11/2017 10/11/2017
Progress Inspection Partial Pass 10/19/2017 (10:00 - 12:00) 10/19/2017 10/19/2017
Ok to cover theaters 4,5,6 and add a head to 3 by wing wall.
Framing Inspection Partial Pass 10/19/2017 (10:00 - 12:00) 10/19/2017 10/19/2017
Corrections:


Miscellaneous/Other
Comment Only
10/19/2017
Theaters 4,5&6 ok to pad ceilings. Theaters 9-14, 1st layer gypsum approved. Wall Framing at mezzanine level approved.

Framing Inspection Partial Pass 10/25/2017 (12:30 - 2:30) 10/25/2017 10/25/2017
Corrections:


Miscellaneous/Other
Comment Only
10/25/2017
Walls at west side approved. Bulkhead framing at market place approved... remove the supports that are attached to duct supports.

Framing Inspection Partial Pass 11/1/2017 (12:30 - 2:30) 11/1/2017 11/01/2017
Corrections:


Miscellaneous/Other
Comment Only
11/01/2017
West condiments ceiling, east condiments ceilings approved to cover.

Framing Inspection Partial Pass 11/14/2017 (8:00 - 10:00) 11/14/2017 11/14/2017
Corrections:


Miscellaneous/Other
Comment Only
11/14/2017
East spillway and theaters entry,s ceilings. Ok to cover. East lobby and condiments ceilings, market place tarten ceiling area.... theaters 9-14 ceilings. Ok to cover.

Framing Inspection Partial Pass 11/17/2017 (10:00 - 12:00) 11/17/2017 11/17/2017
Corrections:


Miscellaneous/Other
Comment Only
11/17/2017
East and west spillways and theater entry’s ...mall soffit. Approved to cover.

Framing Inspection Partial Pass 12/6/2017 (8:00 - 10:00) 12/6/2017 12/06/2017
Corrections:


Miscellaneous/Other
Comment Only
12/06/2017
South market, main kitchen, west storages, and east offices above ceiling approved , pending individual corrections to rated walls as labeled on sign off sheet at each location.

Framing Inspection Partial Pass 1/2/2018 (8:00 - 10:00) 1/2/2018 01/02/2018
Contractor rescheduled on 12/29/2017. ajacobson 12/29/2017 10:25 AM Contractor called to scheduled. Appeared to be pending. Contractor said on 12/27/17 he canceled the 12/28/17 inspections. ajacobson 12/29/2017 10:23 AM
Corrections:


Miscellaneous/Other
Comment Only
01/02/2018
ceilings in dry storage / entry, and ticketing ... approved. Speaker wiring is still to be corrected with rating for plenum.

Framing Inspection Failed 1/31/2018 (10:00 - 12:00) 1/31/2018 01/31/2018
Corrections:


Miscellaneous/Other
Comment Only
01/31/2018
Fireproofing patching is needed to the supporting members in the ceilings above both locker rooms. Call for reinspection when done.

Framing Inspection Partial Pass 2/6/2018 (8:00 - 10:00) 2/6/2018 02/06/2018
Corrections:


Miscellaneous/Other
Comment Only
02/06/2018
Fireproofing patched in the above ceiling of the be upper level bathrooms/ locker rooms... ok to pad out ceilings.

Building Final Inspection Partial Pass 04/03/2018
Corrections:


Miscellaneous/Other
Comment Only
04/03/2018
All testing completed with fire and smoke control, EM lighting approved. This is an approval for training and setup of the kitchens. Approval is pending the approval from Environmental Health, bar training and setup is pending licensing and Environmental Health approval. Will need to recheck some areas within this buildout for other items needed to be addressed for the full final. This inspection is only to release the kitchen and cooking areas for training and setup.

Progress Inspection Partial Pass 4/4/2018 (10:00 - 12:00) 4/4/2018 04/04/2018
Corrections:


Miscellaneous/Other
Comment Only
04/04/2018
Started to go through the new buildout to view all work and code compliance. A list of items to be addressed was sent to contractor. This is an ongoing progress inspection for the potential final of permit.

Building Final Inspection Partial Pass 4/25/2018 (8:00 - 10:00) 4/25/2018 04/25/2018
PCL contractor canceled inspection final (bldg and fire). OK per Duke. ajacobson 04/19/2018 4:31 PM
Corrections:


Miscellaneous/Other
Outstanding
04/25/2018
Add the 2 directional exit signage and lower coat hooks in womans bath to comply with accessibility.

Miscellaneous/Other
Comment Only
04/25/2018
Approved for friends and family soft viewing, full occupancy will be granted when all items are completed and inspected.

Fire Inspection Final Passed 4/25/2018 (8:00 - 10:00) 4/25/2018 04/26/2018
PCL contractor canceled inspection final (bldg and fire). OK per Duke. ajacobson 04/19/2018 4:31 PM
Building Final Inspection Passed 04/26/2018
OK to issue COO per J.Aaron. Moe Amanda 04/26/2018 3:57 PM
Corrections:


Miscellaneous/Other
Comment Only
04/26/2018
Final approved. One condition remains : Replace the 2 added directional exit signs with an arrowed directional sign that points to the front exit doors, ( these signs are already ordered and will be in within 3 weeks).