PRBD201704087
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Failed | 8/21/2017 (12:30 - 2:30) | 8/21/2017 | 08/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/21/2017
Contractor went home, space locked. Reschedule inspection.
|
||||
Framing Inspection | Partial Pass | 8/23/2017 (8:00 - 10:00) | 8/23/2017 | 08/23/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/23/2017
Wall framing approved to cove, leave open the 3 interior columns for inspection of fire proofing patching.
|
||||
Insulation Inspection | Partial Pass | 8/28/2017 (10:00 - 12:00) | 8/28/2017 | 08/28/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/28/2017
Fire proofing approved, ok to cover columns. Storefront cannot have any wood combustibles in the framing. Metal to be used for hanging door and gypsum needs to be installed prior to FRT plywood.
|
||||
Framing Inspection | Passed w/ Conditions | 8/31/2017 (8:00 - 10:00) | 8/31/2017 | 08/31/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/31/2017
Approved to cover all ceilings except for rear ceiling by passageway door pending electrical and sprinkler inspection for that portion of ceiling. Storefront approved to cover .
|
||||
Fire Inspection Final | Passed | 10/25/2017 (2:30 - 3:30) | 10/25/2017 | 10/25/2017 |
Building Final Inspection | Partial Pass | 10/25/2017 (2:30 - 3:30) | 10/25/2017 | 10/25/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/25/2017
1) install trap wraps to sinks. 2) electrical final needed for C.O. 3) rear door to latch.
Approved to stock and train, call for C.O final when completed.
|
||||
Building Final Inspection | Passed | 10/27/2017 (10:00 - 12:00) | 10/27/2017 | 10/27/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/27/2017
All items completed. Final approved
|