PRBD201704195
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 8/7/2017 (12:30 - 2:30) | 8/7/2017 | 08/07/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/07/2017
Wall framing approved to cover. Corrections at stair 2 hour wall and back of elevator shaft wall for 1st layer of gypsum to be inspected and putty pads added to 3 boxes. Patch fireproofing at center column. To be checked at reinspection to cover those ares.
|
||||
Framing Inspection | Partial Pass | 8/15/2017 (8:00 - 10:00) | 8/15/2017 | 08/15/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/15/2017
Putty pads added to electrical boxes at shaft wall.... approved to cover shaft walls. Hard lids approved to cover.
|
||||
Above Ceiling Inspection | Passed | 9/14/2017 (2:30 - 3:30) | 9/14/2017 | 09/14/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/14/2017
Approved to cover ceilings.
|
||||
Fire Inspection Final | Failed | 9/14/2017 (10:00 - 12:00) | 9/14/2017 | 09/14/2017 |
Corrections:
Miscellaneous/Other
Carried Forward
09/14/2017
Need to finish installing sprinkler head in wood cloud in conference room.
Need to finish installing all furniture, fixture, equipment, flooring, etc.
Need to test fire alarm system.
Need all other trade inspection finals.
|
||||
Progress Inspection | Partial Pass | 9/21/2017 (12:30 - 2:30) | 9/21/2017 | 09/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/21/2017
Progress of work. Complete work and inspections for setup of occupancy inspection on 9/22.
|
||||
Fire Inspection Final | Passed | 9/22/2017 (10:00 - 12:00) | 9/22/2017 | 09/22/2017 |
Corrections:
Miscellaneous/Other
Outstanding
09/14/2017
Need to finish installing sprinkler head in wood cloud in conference room.
Need to finish installing all furniture, fixture, equipment, flooring, etc.
Need to test fire alarm system.
Need all other trade inspection finals.
|
||||
Building Final Inspection | Partial Pass | 9/22/2017 (10:00 - 12:00) | 9/22/2017 | 09/22/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/22/2017
Approved for temp occupancy for staff to come in and work this weekend under these conditions... 1) contractor to clean up and remove tools/carts. 2) tempered glass for doors to be installed for full occupancy. 3) patching to be done at kitchenette outlets and outlets to be fully installed by the end of day. 4) instant hot heater wiring to be terminated in a junction box till unit arrives and is installed. Call for full final inspection when all the remaining work is complete.
|
||||
Building Final Inspection | Passed | 10/12/2017 (8:00 - 10:00) | 10/12/2017 | 10/12/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/12/2017
All work and inspections completed. Final approved for occupancy.
|