Permit Application Status

PRBD201704401


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201704401
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Tenant Improvements - 336 East Broadway
05/31/2017
06/26/2017
12/02/2021
08/17/2017

Locations

Permits

Permit Number: PRBD201704401

Building
Finaled
06/26/2017
12/02/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 7/5/2017 (10:00 - 12:00) 7/5/2017 07/05/2017
Corrections:


Miscellaneous/Other
Comment Only
07/05/2017
Storefront framing, walls, and one framed up column. ...ok to cover. Floor holes approved to fill with concrete.

Framing Inspection Partial Pass 7/7/2017 (8:00 - 10:00) 7/7/2017 07/07/2017
Above ceiling
Corrections:


Miscellaneous/Other
Comment Only
07/07/2017
Verbal correction to add framing member on each wall of column wrap, also to fireproof patch to stud attachment to column. Ok to cover columns.

Framing Inspection Passed 7/19/2017 (12:30 - 2:30) 7/19/2017 07/19/2017
Corrections:


Miscellaneous/Other
Comment Only
07/19/2017
Approved to cover ceilings in Black light golf space.

Fire Inspection Final Failed 8/9/2017 (8:00 - 10:00) 8/9/2017 (AM) 08/09/2017
Back exit door is not contrasting to the back ground. Contractor and MOA working on a solution. Current plan is to leave the door black and paint the frame/components fluorescent green. Contractor will advise on final plan and schedule inspection for verification.
Building Final Inspection Failed 8/9/2017 (8:00 - 10:00) 8/9/2017 08/09/2017
Corrections:


Miscellaneous/Other
Comment Only
08/09/2017
rear door to be contrasting color and shut and latch. Install transition to rear door carpet. Relocate curb stone out of egress path to rear exit. Electrical final needed, pending inspection scheduled today. No public opening at this time.

Fire Inspection Final Passed 8/9/2017 08/09/2017
Back exit door painted and is acceptable.
Building Final Inspection Partial Pass 08/09/2017
Corrections:


Miscellaneous/Other
Comment Only
08/09/2017
Electrical final needed and recheck by fire. All have approved a temp for opening to public with a reinspection for final within 7 days.

Building Final Inspection Passed 8/17/2017 (10:00 - 12:00) 8/17/2017 08/17/2017
Corrections:


Miscellaneous/Other
Comment Only
08/17/2017
Final approved for occupancy