Permit Application Status

PRBD201704491


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201704491
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Tenant fit-out which requires demo of existing partitions, finishes and fixtures. Construct new drywall partitions, finishes and fixtures as per plans and per code. Five Below - MOA
06/02/2017
07/26/2017
04/28/2018
10/30/2017

Locations

Permits

Permit Number: PRBD201704491

Building
Finaled
07/26/2017
04/28/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 8/8/2017 (10:00 - 12:00) 8/8/2017 08/08/2017
Corrections:


Miscellaneous/Other
Comment Only
08/08/2017
Approved to cover suite dismissing walls only pending electrical inspection approval.

Framing Inspection Partial Pass 8/28/2017 (8:00 - 10:00) 8/28/2017 08/28/2017
Corrections:


Miscellaneous/Other
Comment Only
08/28/2017
Framing approved . Plumber to fire caulk copper pipe... send picture to inspector. Walls only, and room ceilings, no storefront.

Framing Inspection Passed w/ Conditions 9/14/2017 (10:00 - 12:00) 9/14/2017 09/14/2017
Corrections:


Miscellaneous/Other
Comment Only
09/14/2017
Fireproofing patching approved at locations designated. Storefront approved to cover, pending electrical inspection.

Progress Inspection Passed w/ Conditions 10/19/2017 (8:00 - 10:00) 10/19/2017 10/19/2017
Corrections:


Miscellaneous/Other
Comment Only
10/19/2017
Approval for stocking of product. Final inspections by electrical, fire and bldg. to follow.

Building Final Inspection Partial Pass 10/30/2017 (10:00 - 12:00) 10/30/2017 10/30/2017
Corrections:


Miscellaneous/Other
Comment Only
10/30/2017
Adjust rear double doors to shut and latch, install smoke seals to both exit doors at passageway. Approved to open, final is pending these corrections.

Fire Inspection Final Passed 10/30/2017 (10:00 - 12:00) 10/30/2017 (AM) 10/30/2017
Building Final Inspection Passed 10/30/2017
Corrections:


Miscellaneous/Other
Comment Only
10/30/2017
Smoke seals installed. Final approved