Permit Application Status

PRBD201704689


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201704689
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Construct a new retail service bakery. Carlo's Bake Shop at MOA, 335 North Garden.
06/06/2017
07/11/2017
06/04/2024
10/05/2017

Locations

Permits

Permit Number: PRBD201704689

Building
Finaled
07/11/2017
06/04/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 7/28/2017 (12:30 - 2:30) 7/28/2017 07/28/2017
Corrections:


Miscellaneous/Other
Comment Only
07/28/2017
Progress inspection, allow contractor to one side walls.

Framing Inspection Partial Pass 8/8/2017 (8:00 - 10:00) 8/8/2017 08/08/2017
Corrections:


Miscellaneous/Other
Comment Only
08/08/2017
Approved to cover walls only. Photograph and send inspector pictures of the 1/2 copper trap primer piping firecaulking in 2 locations.

Framing Inspection Partial Pass 8/16/2017 (10:00 - 12:00) 8/16/2017 08/16/2017
Corrections:


Miscellaneous/Other
Comment Only
08/16/2017
Soffits approved to cover pending sprinkler inspection. Fireproofing patching to be inspected.

Above Ceiling Inspection Passed w/ Conditions 9/19/2017 (2:30 - 3:30) 9/19/2017 09/18/2017
Corrections:


Miscellaneous/Other
Comment Only
09/18/2017
Above ceiling approved to cover A.C.T ceiling as per sprinkler inspection approval.

Fire Inspection Final Failed 9/20/2017 (10:00 - 12:00) 9/20/2017 09/20/2017
Building Final Inspection Failed 9/20/2017 (10:00 - 12:00) 9/20/2017 09/20/2017
Corrections:


Miscellaneous/Other
Comment Only
09/20/2017
1) Sprinklers needed in coolers. Fire inspector to reinspect. 2) complete overhead work and cleaning. 3) roof top unit to be tested and functioning properly. Makeup air in space to also be balanced. 4) complete sealing and firestops at the removed penetrations on the passageway wall in passageway. (Upper section of wall to be patched in as well). No stocking or setup, no temp for any use at this time.

Building Final Inspection Failed 9/21/2017 (8:00 - 10:00) 9/21/2017 09/21/2017
Corrections:


Miscellaneous/Other
Comment Only
09/21/2017
No change since inspection on 9/20/17 except sprinklers were installed in the coolers. Approved to stock coolers as needed. Still not approved for stock and training.

Temporary Certificate of Occupancy Inspection Partial Pass 9/22/2017 (12:30 - 2:30) 9/22/2017 09/22/2017
Corrections:


Miscellaneous/Other
Comment Only
09/22/2017
E.H requirements and corrections to apply. mechanical with exhaust unit to be addressed. As per joint agreement with Mechanical inspector and E.H. Approved to stock and train and prepare goods.

Building Final Inspection VOID 09/28/2017
Temporary Certificate of Occupancy Inspection VOID 09/28/2017
Fire Inspection Final Passed 9/21/2017 (8:00 - 10:00) 9/21/2017 09/29/2017
Building Final Inspection Partial Pass 9/29/2017 (10:00 - 12:00) 9/29/2017 09/29/2017
Corrections:


Miscellaneous/Other
Comment Only
09/29/2017
1) 3ft. Clearance needed at panel box, electrical inspection needed to verify breaker lockouts.2) E.H. To do follow up inspection and final permit. Approved to open to public on T.C.O

Fire Inspection Final Passed 10/5/2017 (10:00 - 12:00) 10/5/2017 10/05/2017
Building Final Inspection Passed 10/5/2017 (10:00 - 12:00) 10/5/2017 10/05/2017
Corrections:


Miscellaneous/Other
Comment Only
10/05/2017
All inspections completed, electrical to final permit as per pictures of breaker locks. Final C.O. Approved