PRBD201704689
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 7/28/2017 (12:30 - 2:30) | 7/28/2017 | 07/28/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/28/2017
Progress inspection, allow contractor to one side walls.
|
||||
| Framing Inspection | Partial Pass | 8/8/2017 (8:00 - 10:00) | 8/8/2017 | 08/08/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/08/2017
Approved to cover walls only. Photograph and send inspector pictures of the 1/2 copper trap primer piping firecaulking in 2 locations.
|
||||
| Framing Inspection | Partial Pass | 8/16/2017 (10:00 - 12:00) | 8/16/2017 | 08/16/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/16/2017
Soffits approved to cover pending sprinkler inspection. Fireproofing patching to be inspected.
|
||||
| Above Ceiling Inspection | Passed w/ Conditions | 9/19/2017 (2:30 - 3:30) | 9/19/2017 | 09/18/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/18/2017
Above ceiling approved to cover A.C.T ceiling as per sprinkler inspection approval.
|
||||
| Fire Inspection Final | Failed | 9/20/2017 (10:00 - 12:00) | 9/20/2017 | 09/20/2017 |
| Building Final Inspection | Failed | 9/20/2017 (10:00 - 12:00) | 9/20/2017 | 09/20/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/20/2017
1) Sprinklers needed in coolers. Fire inspector to reinspect. 2) complete overhead work and cleaning. 3) roof top unit to be tested and functioning properly. Makeup air in space to also be balanced. 4) complete sealing and firestops at the removed penetrations on the passageway wall in passageway. (Upper section of wall to be patched in as well). No stocking or setup, no temp for any use at this time.
|
||||
| Building Final Inspection | Failed | 9/21/2017 (8:00 - 10:00) | 9/21/2017 | 09/21/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/21/2017
No change since inspection on 9/20/17 except sprinklers were installed in the coolers. Approved to stock coolers as needed. Still not approved for stock and training.
|
||||
| Temporary Certificate of Occupancy Inspection | Partial Pass | 9/22/2017 (12:30 - 2:30) | 9/22/2017 | 09/22/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/22/2017
E.H requirements and corrections to apply. mechanical with exhaust unit to be addressed. As per joint agreement with Mechanical inspector and E.H. Approved to stock and train and prepare goods.
|
||||
| Building Final Inspection | VOID | 09/28/2017 | ||
| Temporary Certificate of Occupancy Inspection | VOID | 09/28/2017 | ||
| Fire Inspection Final | Passed | 9/21/2017 (8:00 - 10:00) | 9/21/2017 | 09/29/2017 |
| Building Final Inspection | Partial Pass | 9/29/2017 (10:00 - 12:00) | 9/29/2017 | 09/29/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/29/2017
1) 3ft. Clearance needed at panel box, electrical inspection needed to verify breaker lockouts.2) E.H. To do follow up inspection and final permit. Approved to open to public on T.C.O
|
||||
| Fire Inspection Final | Passed | 10/5/2017 (10:00 - 12:00) | 10/5/2017 | 10/05/2017 |
| Building Final Inspection | Passed | 10/5/2017 (10:00 - 12:00) | 10/5/2017 | 10/05/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/05/2017
All inspections completed, electrical to final permit as per pictures of breaker locks. Final C.O. Approved
|
||||