PRBD201705287
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 9/13/2017 (8:00 - 10:00) | 9/13/2017 | 09/13/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/13/2017
1st layer gypsum at theatre 14 & 13 at wall approved. Foam and reinforcing at 3 theaters ok for concrete.
|
||||
Framing Inspection | Partial Pass | 9/19/2017 (10:00 - 12:00) | 9/19/2017 | 09/19/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/19/2017
Approved to cover walls in theaters 9,10&11. Kitchen walls ok to cover. Theaters 4,5&6 ok for concrete. Theatre 9 exposed beam to be fireproofed, reinspection of this required.
|
||||
Framing Inspection | Partial Pass | 9/25/2017 (8:00 - 10:00) | 9/25/2017 | 09/25/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/25/2017
Fireproofing at beam in theatre 9 approved. Framing of sound wall in theatre 10, approved. low header repaired and approved. Approved to cover furred walls.
|
||||
Framing Inspection | Failed | 10/3/2017 (8:00 - 10:00) | 10/3/2017 | 10/03/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/03/2017
Soffit / ceiling in theater 7 cannot support off duct or its supports unless an engineer has done the calculations and design to allow this. 1) resuppot framing with heavier gage members that can span the duct or install supports to accommodate the framing and weight of a double layered ceiling.
|
||||
Framing Inspection | Partial Pass | 10/05/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/05/2017
Soffit in theater 7 has been resupported, approved to cover.
|
||||
Framing Inspection | Partial Pass | 10/10/2017 (8:00 - 10:00) | 10/10/2017 | |
Corrections:
Miscellaneous/Other
Comment Only
10/10/2017
East bathrooms walls approved to cover. Spillway wall framing approved to cover. Need to reinspect under stairs of the exposed foam that needs to be covered. Provide clean out access to plumbing and firestop through floor penetration up in spillway location. Reinspection required.
|
||||
Framing Inspection | Partial Pass | 11/06/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/06/2017
Main south existing wall framing and firestops approved to cover.
|
||||
Building Final Inspection | Passed | 04/03/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/03/2018
Final for this permit approved, see permit 201703863.
|