PRBD201705325
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Passed | 11/13/2017 (2:30 - 3:30) | 11/13/2017 | 11/13/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/13/2017
Footings approved
|
||||
Building Final Inspection | Partial Pass | 1/24/2018 (2:30 - 3:30) | 1/24/2018 | 01/24/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/24/2018
All framing of this structure is approved. The metal roof has not yet been installed due to material back order. This is scheduled to be installed on 1/31/18. Contractor will provide pictures of the completed roof to inspector when done.
|
||||
Building Final Inspection | Passed | 01/30/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
01/30/2018
Received detailed pictures of the roof metal installed onto the structure, the installation is approved and permit can be closed out with a “final”.
|