Permit Application Status

PRBD201706200


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201706200
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Modify existing space on the lower level of the Mall of America to construct a 1277 Sq Ft Server Room for antenna distribution front-end equipment. MOA - Server Room DAS (Distributed Antenna System).
07/14/2017
08/10/2017
03/30/2019
10/01/2018

Locations

Permits

Permit Number: PRBD201706200

Building
Finaled
08/10/2017
03/30/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 9/6/2017 (12:30 - 2:30) 9/6/2017 09/06/2017
Framing; Exterior steel stud walls with existing block walls, create data room, with new iron mezzanine, and entry door. Framing of new walls only. - ok. Partial approved. A) Call for existing ceiling steel beams w/ existing fireproofing for patching. Cafco brand hand patch fireproofing recommended. Match existing fireproofing depths. LOCATION-LOWER LEVEL EAST. Take back house elevator 12, to lower level.
Framing Inspection Partial Pass 10/23/2017 (8:00 - 10:00) 10/23/2017 10/23/2017
Corrections:


Miscellaneous/Other
Comment Only
10/23/2017
Wall framing approved. Note: fireproofing in both room areas to be patched at beams. Reinspect at above ceiling inspection.

Above Ceiling Inspection Partial Pass 10/31/2017 (8:00 - 10:00) 10/31/2017 10/31/2017
Corrections:


Miscellaneous/Other
Comment Only
10/31/2017
Above ceiling : patched fireproofing, and fire stops approved. Note; the cable trays will need fire stopped and viewed prior to final inspection . Guardrails to be installed at openings of the mezzanine.

Progress Inspection Partial Pass 11/21/2017 (8:00 - 10:00) 11/21/2017 11/21/2017
Corrections:


Miscellaneous/Other
Comment Only
11/21/2017
Viewed firestops at head end room, and 1st floor back of house locations. Contractor also took photos of firestops at mall bulkheads and inside tenant Suites. Approved all viewed, continue to provide photos as what is yet to view.

Fire Inspection Final Not Ready 11/27/2017 (8:00 - 10:00) 11/27/2017 11/27/2017
Corrections:


Miscellaneous/Other
Carried Forward
11/27/2017
All doors need to close, latch, and have smoke gaskets. Need knox box installed and EPO procedures posted.

Building Final Inspection Partial Pass 11/27/2017 (8:00 - 10:00) 11/27/2017 11/27/2017
Corrections:


Miscellaneous/Other
Outstanding
11/27/2017
1) provide smoke seal at secondary door exit. 2) emergencyshut down procedures needed for fire department procedures. 3) install Knox box as required by fire inspection. 4) mezzanine needs guards and possible hatch cover, engineer to design and submit to city for review. Details with battery boxes in ramp to be addressed along with 4TH floor gantry. Approved for temp use with above items to be addressed ASAP. City may revoke temp use if above items are not taken care of or addressed in a timely manor, inspector will confirm with building official on these issues. All fire stops within mall as pertaining to the scope of this permit are approved and pictures provided for areas that are not accessible to view.

Building Final Inspection Partial Pass 12/14/2017 (10:00 - 12:00) 12/14/2017 12/14/2017
Corrections:


Miscellaneous/Other
Outstanding
12/14/2017
Guardrails and hatch cover installed at mezzanine. Smoke seal at door approved. Shut down instructions to still be supplied to its fire inspector and this permit still remains open for the remaining completion of the 4th floor gantry area with this project.

Fire Inspection Final Partial Pass 12/14/2017 (10:00 - 12:00) 12/14/2017 (AM) 12/14/2017
Corrections:


Miscellaneous/Other
Outstanding
11/27/2017
All doors need to close, latch, and have smoke gaskets. Need knox box installed and EPO procedures posted.

Progress Inspection Passed 4/19/2018 (12:30 - 2:30) 4/19/2018 04/19/2018
Corrections:


Miscellaneous/Other
Comment Only
04/19/2018
Stairwell ... all demo completed and rated walls at back to the 2 hour rating and firestops at penetrations completed . Approved to close out his permit once the permit for the remaining work of separation of the mezzanine is issued.

Building Final Inspection Passed 10/01/2018
Corrections:


Miscellaneous/Other
Comment Only
10/01/2018
All associated work for this permit completed, see permit 201805217 for completion of gantry work inspections. Final for this permit approved.