PRBD201706442
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 9/25/2017 (12:30 - 2:30) | 9/25/2017 | 09/25/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/25/2017
Approved to cover all walls within space. Storefront to be inspected by fire inspector, and framing. Sprinkler, abandoned wiring and lighting to be removed in storefront and reinspected.
|
||||
Framing Inspection | Passed w/ Conditions | 9/28/2017 (8:00 - 10:00) | 9/28/2017 | 09/28/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/28/2017
Storefront framing approved, leave open for sprinkler inspection scheduled for 9/29 before covering.
|
||||
Fire Inspection Final | Passed | 10/25/2017 (8:00 - 10:00) | 10/25/2017 | 10/25/2017 |
Building Final Inspection | Partial Pass | 10/26/2017 (8:00 - 10:00) | 10/26/2017 | 10/26/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/26/2017
Approved to stock and merchandise.
Note: all setup to be completed for final inspection prior to reopening.
|
||||
Building Final Inspection | Passed | 11/9/2017 (2:30 - 3:30) | 11/9/2017 | 11/09/2017 |