PRBD201706601
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 8/23/2017 (8:00 - 10:00) | 8/24/2017 | 08/24/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/24/2017
Approved to cover storefront and walls.
|
||||
Building Final Inspection | Partial Pass | 9/28/2017 (10:00 - 12:00) | 9/28/2017 | 09/28/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/28/2017
Prefinal approved. Ok to setup space. E.H. To do inspection. Call for final when ready.
|
||||
Building Final Inspection | Passed | 10/5/2017 (10:00 - 12:00) | 10/5/2017 | 10/05/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/05/2017
Final approved .
|
||||
Fire Inspection Final | Passed | 10/5/2017 (10:00 - 12:00) | 10/5/2017 | 10/05/2017 |