PRBD201706784
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 10/12/2017 (12:30 - 2:30) | 10/12/2017 | 10/12/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/12/2017
Men’s and women’s bathrooms in the water park in 1st level....framing and firestops approved. Note: there are 6 holes in floor rhat need to be filled with concrete to maintain rating. Reinspect at next inspection.
Above ceiling in lower level: area “A” lower level office space opproved to pad out ceilings.
|
||||
| Framing Inspection | Partial Pass | 11/3/2017 (12:30 - 2:30) | 11/3/2017 | 11/03/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/03/2017
Lower level: men’s ambulatory stall hook to be no more that 48” in height. Women’s bathroom ambulatory stall hook to be no more than 48” in height and mirror to be installed at sink counter. Conference center needs occupancy load sign.
Board room approved pending electrical hookup and inspection for the table. Office are “A” approved for final. Electrical room approved. End pump room... patch holes in rated wall.
Approved for the temp occupancy of the hotel staff to come in and set up with offices. Exiting is approved and contractor has designated entry and exit for these staff personal to use without going through construction areas. All inspections for thes areas are completed with exception of the board room table electrical hookup. The accessible items in bathrooms will be completed today, 11/3/17.
|
||||
| Framing Inspection | Passed | 11/22/2017 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
11/22/2017
See permit PRBD201702744 for other inspection results. All framing completed.
|
||||
| Building Final Inspection | Partial Pass | 11/22/2017 | ||
|
Corrections:
Miscellaneous/Other
Outstanding
11/22/2017
Basement t garage firestops are being completed with the mineral wool to the firestop piping that was not completed.to be reinspected at final inspection.
|
||||
| Building Final Inspection | Passed | 12/08/2017 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
12/08/2017
Final approved
|
||||