PRBD201707506
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 9/12/2017 (8:00 - 10:00) | 9/12/2017 | 09/12/2017 |
|
Corrections:
Miscellaneous/Other
Outstanding
09/12/2017
Framing - A. Scrim foil exterior perimeter above ceiling. ABOVE CEILING: Patch fireproofing, ceiling 4 inch hole to have mineral wool and fire caulk or fire rated red spray foam. B. Call for above ceiling for electrical, low voltage, HVAC,fire sprinkler, and wall and or above ceiling for plumbing.
|
||||
| Framing Inspection | Partial Pass | 10/4/2017 (10:00 - 12:00) | 10/4/2017 | 10/04/2017 |
|
Corrections:
Miscellaneous/Other
Outstanding
10/04/2017
Patch fireproofing above ceiling, south wall east and west areas, north corridor wall, east area, and above break room marked on plan, and remove wood 2x2 above ceiling north corrridor wall, west end.
|
||||
| Fire Inspection Final | Passed | 10/25/2017 (12:30 - 2:30) | 10/25/2017 | 10/25/2017 |
| Building Final Inspection | Passed | 10/25/2017 (12:30 - 2:30) | 10/25/2017 | 10/25/2017 |
| Framing Inspection | Passed | 10/25/2017 (12:30 - 2:30) | 10/25/2017 | 10/25/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/25/2017
Final for framing and above ceiling patching of fireproofing. Note- Tim is an awesome field superintendent .
|
||||