Permit Application Status

PRBD201709422


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201709422
Building
Finaled
FELCOR/CSS HOLDINGS SPE
Alteration/Remodel
Assembly, restaurants, bars, banquet halls, nightclubs
Residential, hotels
Interior renovation of the atrium and 1st floor public spaces.
10/04/2017
03/14/2018
03/30/2019

Locations

Permits

Permit Number: PRBD201709422

Building
Finaled
03/14/2018
03/30/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 3/21/2018 (2:30 - 3:30) 3/21/2018 03/21/2018
Corrections:


Miscellaneous/Other
Comment Only
03/21/2018
Remaining partition wall framing in atrium area, approved to cover.

Framing Inspection Partial Pass 3/27/2018 (10:00 - 12:00) 3/27/2018 03/27/2018
Corrections:


Miscellaneous/Other
Comment Only
03/27/2018
Above ceiling in Azalia meeting room approved. Make sure electrical and fire inspections are completed before covering ceilings.

Progress Inspection Partial Pass 3/30/2018 (10:00 - 12:00) 3/30/2018 03/30/2018
Corrections:


Miscellaneous/Other
Comment Only
03/30/2018
Final approved for small, north side, 1st floor conference rooms that are adjacent to the pool.

Progress Inspection Partial Pass 3/30/2018 (10:00 - 12:00) 3/30/2018 03/30/2018
Corrections:


Miscellaneous/Other
Comment Only
03/30/2018
Azeala meeting room... Approved . Once separation from the construction portion of job is installed, this room can be used by public. Occupancy load sign is a temp sign and is installed , this will be replaced with the new one once it comes in.

Progress Inspection Partial Pass 4/3/2018 (10:00 - 12:00) 4/3/2018 04/03/2018
Corrections:


Miscellaneous/Other
Comment Only
04/03/2018
Ceiling framing and above ceiling in fitness center , and willow meeting room. Approved , but cannot cover till electrical and sprinkler has approved to cover. All existing HVAC used and reinstalled.

Progress Inspection Partial Pass 4/9/2018 (10:00 - 12:00) 4/9/2018 04/09/2018
Corrections:


Miscellaneous/Other
Comment Only
04/09/2018
Pre function and willow room .... occupancy signage to be adjusted to reflect the load for each side and max congregate load. Address the exit door wth broken door hinge and smoke seals. Above ceiling in.... office approved to cover.

Progress Inspection Partial Pass 4/11/2018 (8:00 - 10:00) 4/11/2018 04/11/2018
Corrections:


Miscellaneous/Other
Comment Only
04/11/2018
Willow A&B room approved for occupancy. Palm / pre function above ceiling approved.

Progress Inspection Partial Pass 4/12/2018 (2:30 - 3:30) 4/12/2018 04/12/2018
Corrections:


Miscellaneous/Other
Comment Only
04/12/2018
Palm meeting room, office, and fitness. Approved for public use.

Progress Inspection Partial Pass 4/26/2018 (2:30 - 3:30) 4/26/2018 04/26/2018
Corrections:


Miscellaneous/Other
Comment Only
04/26/2018
Pool area... signage for occupancy load installed at 34 persons. Accessible chair lifts tested and working. Pool heaters are located in the existing location in a room in the laundry room, and they are supported above ceiling with exterior are exchange ducting to cool equipment. Approved to open pool pending the correction of the walk-in shower w/ the handheld slide control that will be changed out ASAP and reinspected.

Miscellaneous/Other
Outstanding
04/26/2018
Change out hand shower at walk in shower of pool to comply with accessibility requirements... “ no gripping, grasping, flipping of the wrist to operate the raise/ lower device” .

Progress Inspection Partial Pass 4/30/2018 (10:00 - 12:00) 4/30/2018 04/27/2018
Corrections:


Miscellaneous/Other
Comment Only
04/27/2018
Handheld shower at pool area has been changed out and now meets accessibility requirements. Approved for public use.

Framing Inspection Partial Pass 5/8/2018 (8:00 - 10:00) 5/8/2018 05/08/2018
Corrections:


Miscellaneous/Other
Comment Only
05/08/2018
Interior and shell framing of “ Cook to Order” approved as per the plans and details. Of to cover.

Progress Inspection Partial Pass 5/10/2018 (12:30 - 2:30) 5/10/2018 05/10/2018
Corrections:


Miscellaneous/Other
Comment Only
05/10/2018
Wall framing to resturant approved. Approved to final the bathrooms for public use.

Progress Inspection Partial Pass 5/17/2018 (2:30 - 3:30) 5/17/2018 05/17/2018
Corrections:


Miscellaneous/Other
Comment Only
05/17/2018
Progress for seating area of atrium, corrections given to contractor for the turnover of this section. Reinspect on 5/18

Progress Inspection Partial Pass 5/18/2018 (7:00 - 8:00) 5/18/2018 05/18/2018
Corrections:


Miscellaneous/Other
Comment Only
05/18/2018
Lower seating area has approval for public use and access. There are barriers installed to separate and keep public out and away from the upper seating and the ongoing buildout construction. Approved!

Progress Inspection VOID 5/18/2018 (7:00 - 8:00) 5/18/2018 05/21/2018
Framing Inspection Partial Pass 5/23/2018 (10:00 - 12:00) 5/23/2018 05/23/2018
Corrections:


Miscellaneous/Other
Comment Only
05/23/2018
Wall framing in the restaurant approved . Call for ceiling framing inspection after the trades inspections are completed.

Progress Inspection Partial Pass 5/31/2018 (10:00 - 12:00) 5/31/2018 05/31/2018
Corrections:


Miscellaneous/Other
Comment Only
05/31/2018
Pending approval from electrical inspection, the upper seating area in the atrium may be open for public use. The beverage stations may also be used , per Environmental Health approval and follow up inspection for the holes in the cabinets. Temp bar area may not be used till a portable hand sink is brought in, as per Environmental Health requirements. Cook to order ceiling framing is approved, but cannot be covered till fire sprinkler inspection is approved... this inspection is scheduled for 6/1/18. Determination needed if sprinkler coverage is needed with the enclosed ceiling space. Leave open till sprinkler inspection is approved.

Progress Inspection Partial Pass 6/20/2018 (10:00 - 12:00) 6/20/2018 06/20/2018
Corrections:


Miscellaneous/Other
Comment Only
06/20/2018
Above ceiling in cook to order restaurant approved. Ok to pad out.

Building Final Inspection Partial Pass 08/09/2018
Corrections:


Miscellaneous/Other
Comment Only
08/09/2018
As per E.H. Approval given to open under a temp, for serving the public. Building approval given as well. Fire final needed for full final, with approval from E.H. To be given when permanent sneeze guards are installed.

Progress Inspection Partial Pass 8/9/2018 (12:30 - 2:30) 8/9/2018 08/09/2018
Corrections:


Miscellaneous/Other
Comment Only
08/09/2018
As per E.H. Approved given to open to public for serving. Some minor corrections remain , along with permanent sneeze guards for use. Temp guards are in place. For final... fire inspection and E.H sign off needed. Call when all is completed , testing for fire inspector to be completed as soon as possible.

Progress Inspection Partial Pass 9/11/2018 (10:00 - 12:00) 9/11/2018 09/11/2018
Corrections:


Miscellaneous/Other
Comment Only
09/11/2018
Ceiling framing approved, and finished room approved for use.

Fire Inspection Final Passed 10/1/2018 (10:00 - 12:00) 10/1/2018 10/01/2018
Building Final Inspection Passed 10/1/2018 (10:00 - 12:00) 10/1/2018 10/01/2018
Corrections:


Miscellaneous/Other
Comment Only
10/01/2018
Testing of smoke evacuation system approved. Final approved pending follow up inspection by E.H. For the sneeze guards at buffet.