Permit Application Status

PRBD201710197


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201710197
Building
Finaled
THERMO KING CORPORATION
Alteration/Remodel
Not Required
Remodel existing office area in warehouse
10/23/2017
11/07/2017
07/31/2018
02/01/2018

Locations

Permits

Permit Number: PRBD201710197

Building
Finaled
11/07/2017
07/31/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 11/29/2017 (8:00 - 10:00) 11/29/2017 11/29/2017
Corrections:


Miscellaneous/Other
Comment Only
11/29/2017
Phase 2 framing approved.

Framing Inspection Passed 12/1/2017 (12:30 - 2:30) 12/1/2017 12/01/2017
Corrections:


Miscellaneous/Other
Comment Only
12/01/2017
Wall framing approved for phase 1 & 2. Insulation and poly for exterior walls approved. Call for above ceiling inspection in both phased areas.

Above Ceiling Inspection Partial Pass 12/11/2017 (12:30 - 2:30) 12/11/2017 12/11/2017
Corrections:


Miscellaneous/Other
Comment Only
12/11/2017
Phase 1 above ceiling approved pending fire inspection

Above Ceiling Inspection Passed 12/27/2017 (8:00 - 10:00) 12/27/2017 12/27/2017
Corrections:


Miscellaneous/Other
Comment Only
12/27/2017
Above ceiling approved. Note... Yale mech to patch old openings in roof from the removed unit.

Fire Inspection Final Failed 1/17/2018 (8:00 - 10:00) 1/17/2018 01/17/2018
Corrections:


Miscellaneous/Other
Carried Forward
01/17/2018
Need to final sprinkler/fire alarm permits as needed prior to Fire Marshal Final inspection.

Building Final Inspection Not Ready 1/17/2018 (8:00 - 10:00) 1/17/2018 01/17/2018
Corrections:


Miscellaneous/Other
Comment Only
01/17/2018
Waiting for fire inspection final, and documentation with the egg crate ceiling coverage. Final is pending this issue.

Fire Inspection Final Passed 1/30/2018 (8:00 - 10:00) 01/30/2018
Corrections:


Miscellaneous/Other
Outstanding
01/17/2018
Need to final sprinkler/fire alarm permits as needed prior to Fire Marshal Final inspection.

Building Final Inspection Passed 2/1/2018 02/01/2018
Corrections:


Outstanding
02/01/2018
All inspections are now completed for all trades. Yale Mechanical was made aware by the contractor of the need to insulate the patched over roof opening of the removed rooftop equiptment. Contractor followed up with verification.