PRBD201710239
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Footing Inspection | Partial Pass | 11/29/2017 (8:00 - 10:00) | 11/29/2017 | 11/29/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/29/2017
Footing base for antenna pole at north side of MOA by bus turn around , grounding is welded to the rebar cage.... approved for concrete placement. Frost blankets on site for cold weather protection.
|
||||
Footing Inspection | Passed | 12/1/2017 (10:00 - 12:00) | 12/1/2017 | 12/01/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/01/2017
Two footings in east lot .... grounding is cad welded to rebar, and rebar is as per plan design. Approved for concrete
|