PRBD201800166
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 2/6/2018 (12:30 - 2:30) | 2/6/2018 | 02/06/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/06/2018
Wall Framing approved. Call for trades inspections, sprinkler inspection, and above ceiling inspection for the next step in inspections process.
|
||||
Framing Inspection | Failed | 3/9/2018 (12:30 - 2:30) | 3/9/2018 | 03/09/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/09/2018
Above ceiling is approved for covering pending fire inspection of sprinklers. Call for that inspection and hold off on installing ceiling panels.
|
||||
Fire Inspection Final | Passed w/ Conditions | 4/18/2018 (8:00 - 10:00) | 4/18/2018 | 04/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/18/2018
Fire final performed when sprinkler final was performed. Approved, pending COB Building Inspection.
|
||||
Building Final Inspection | Passed w/ Conditions | 4/18/2018 (8:00 - 10:00) | 4/18/2018 | 04/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/18/2018
Final - A. Accessible restrooms men’s and women’s. - approved.
B. Add signage on the latch side of entry doors as discussed. C.Final fire per Kaiser by Viking. D. All trade permit finals must be
final approved in the city computer system. E. Final - passed with conditions.
|
||||
Framing Inspection | Passed | 10/10/2018 | ||
Building Final Inspection | Passed | 10/10/2018 | ||
Final - close file |