PRBD201800216
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 1/16/2018 (8:00 - 10:00) | 1/16/2018 | 01/16/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/16/2018
Walked through the areas designated on the plans for the event, occupancy load signage needs to be installed at all locations and a door needs to be put in at one of the location on 2nd floor north. Exit signs still in process of install and a directional sign is needed for the larger space on 2nd floor north. North 1st floor has a through floor penetration that is being installed for the power distribution to the space, it needs to be firestopped.
Recheck of the locations is needed to make sure all is compliant.
|
||||
Building Final Inspection | Failed | 1/17/2018 (8:00 - 10:00) | 1/17/2018 | 01/17/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2018
There has been no change as of the inspection done on 1/16/18 with the areas designated as assembly uses for the NFL spaces.
Occupancy load signage is yet to be installed, C 218 & 220 has sprinkler work that needs to be completed and inspected with fire inspector, along with exit signage and door to be added. Other areas to also be completed with exit signage and occupancy load signage.
City to reinspect all the areas when the signage is installed and wired, EM lighting to be checked, and exit doors to be installed to match requirements for occupant load. Any through penetrations that are installed for the use with theses spaces are to be firestopped and also inspected prior to occupancy.
Complete the work necessary for each area and schedule inspections as needed.
|
||||
Building Final Inspection | Partial Pass | 1/19/2018 (8:00 - 10:00) | 1/19/2018 | 01/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/19/2018
Checked all areas designated for use with assembly gathering in the numbered suites/ room areas... all occupancy load signage is installed, the correct number of exits are in place and exiting signage is in place to all the exits. Fire and electrical are following up with their requirements and permits.
Approval is given to allow the vendor to start setup of the draping and other setup they need to do.
|
||||
Miscellaneous/Other
Outstanding
01/19/2018
EM lighting to be checked once the power has been brought in to each space designated for use.
|
||||
Progress Inspection | Partial Pass | 1/24/2018 (10:00 - 12:00) | 1/24/2018 | 01/24/2018 |
Progress inspection only - walkthrough with other at MOA. ajacobson 01/22/2018 2:50 PM | ||||
Corrections:
Miscellaneous/Other
Comment Only
01/24/2018
Walk through on the spaces of the north side.... Due to the piping and draping and the enclosed cubicle rooms , extra exiting signage is needed and adaption to the ceilings of the cubicle rooms for sprinkler protection is needed.
Reinspection needed as the set up is closer to completion. Electrical and fire inspection to also follow up with inspections and any requirements as needed.
Kraft productions is now taking a large space on the north side, exit to be cut in at the dismissing wall to allow access to the NW exit. Exit signage is also to be put back in place at the passageway door.
This is a progress inspection and more inspections are to follow.
|
||||
Building Final Inspection | Passed w/ Conditions | 1/29/2018 (8:00 - 10:00) | 1/29/2018 | 01/29/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/29/2018
went Through all areas and all siting meets requirements.
Approved for temp occupancy of all the NFL location access. Permit final is subject to fire inspection final.
|
||||
Fire Inspection Final | Passed w/ Conditions | 1/29/2018 (8:00 - 10:00) | 1/29/2018 | 02/01/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/01/2018
Approved pending COB Building Department's Final Inspections.
|