PRBD201800228
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 2/8/2018 (10:00 - 12:00) | 2/8/2018 | 02/08/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/08/2018
Structural steel at storefront... approval pending special inspection of the welds.
|
||||
Framing Inspection | Partial Pass | 02/14/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/14/2018
Shaft wall is approved to cover with gypsum. All sheets are set up for the proper staggering of joints.
|
||||
Framing Inspection | Partial Pass | 02/23/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/23/2018
Storefront ceiling approved for gypsum cover.
|
||||
Framing Inspection | Partial Pass | 4/2/2018 (8:00 - 10:00) | 4/2/2018 | 04/02/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/02/2018
Fire stops at through floor penetrations viewed and verified for each piping size requirements. Also viewed through wall firestops to the piping runs. All are for the piping located below the buildout space. Approved.
|
||||
Building Final Inspection | Partial Pass | 4/25/2018 (2:30 - 3:30) | 4/25/2018 | 04/25/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/25/2018
Progress of buildout... cleaning and set up needed. Will follow up with EH for their inspection. All work appears to be as per plan and compliant.
|
||||
Fire Inspection Final | Passed | 4/25/2018 (2:30 - 3:30) | 4/25/2018 | 04/26/2018 |
Fire Inspection Final | Passed | 5/3/2018 (10:00 - 12:00) | 5/3/2018 | 05/03/2018 |
Building Final Inspection | Partial Pass | 5/3/2018 (10:00 - 12:00) | 5/3/2018 | 05/03/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/03/2018
Approved to stock, and train.
|
||||
Miscellaneous/Other
Outstanding
05/03/2018
1) correct holes at passageway of the removed piping and such.
2) final needed by Environmental Health for the building final.
|
||||
Building Final Inspection | Partial Pass | 5/9/2018 (8:00 - 10:00) | 5/9/2018 | 05/09/2018 |
Corrections:
Miscellaneous/Other
Outstanding
05/09/2018
Bar and seating across does not provide for accessibility. The patio will have a table designated for accessibility, it needs to be labeled.
The door floor set guide for the glass storefront doors needs to be transitioned due to the height, and requirements for access heights.
|
||||
Miscellaneous/Other
Comment Only
05/09/2018
The access panel at 3rd floor shaft has been corrected, and the openings at the passageway. Approved
|
||||
Building Final Inspection | Failed | 5/16/2018 (8:00 - 10:00) | 5/16/2018 | 05/16/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/16/2018
The door guide/ transition at storefront still needs to be addressed further. Floor was floated and feathered to the bottom of transition but does not correct the height issue with the transition. Contractor will float and feather from transition back , at both sides to achieve compliance.
|
||||
Building Final Inspection | Partial Pass | 5/18/2018 (8:00 - 10:00) | 5/18/2018 | 05/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/18/2018
The area built up at storefront threshold appears to be code compliant. Contractor to complete the finish and feathering of edges for the next scheduled inspection
|
||||
Building Final Inspection | Passed | 5/21/2018 (8:00 - 10:00) | 5/21/2018 | 05/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/21/2018
Floor at the Transition has been floated to top of transition and feathered back in a ramp style. This meets the intent of the code.
Final approved, ok to open to public.
|