Permit Application Status

PRBD201800228


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201800228
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Wahlburgers MOA New restaurant space 234 North Garden. Separate framing permit issued per Duke Johnson to get work started.
01/09/2018
02/02/2018
11/17/2018
05/21/2018

Locations

Permits

Permit Number: PRBD201800228

Building
Finaled
02/02/2018
11/17/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 2/8/2018 (10:00 - 12:00) 2/8/2018 02/08/2018
Corrections:


Miscellaneous/Other
Comment Only
02/08/2018
Structural steel at storefront... approval pending special inspection of the welds.

Framing Inspection Partial Pass 02/14/2018
Corrections:


Miscellaneous/Other
Comment Only
02/14/2018
Shaft wall is approved to cover with gypsum. All sheets are set up for the proper staggering of joints.

Framing Inspection Partial Pass 02/23/2018
Corrections:


Miscellaneous/Other
Comment Only
02/23/2018
Storefront ceiling approved for gypsum cover.

Framing Inspection Partial Pass 4/2/2018 (8:00 - 10:00) 4/2/2018 04/02/2018
Corrections:


Miscellaneous/Other
Comment Only
04/02/2018
Fire stops at through floor penetrations viewed and verified for each piping size requirements. Also viewed through wall firestops to the piping runs. All are for the piping located below the buildout space. Approved.

Building Final Inspection Partial Pass 4/25/2018 (2:30 - 3:30) 4/25/2018 04/25/2018
Corrections:


Miscellaneous/Other
Comment Only
04/25/2018
Progress of buildout... cleaning and set up needed. Will follow up with EH for their inspection. All work appears to be as per plan and compliant.

Fire Inspection Final Passed 4/25/2018 (2:30 - 3:30) 4/25/2018 04/26/2018
Fire Inspection Final Passed 5/3/2018 (10:00 - 12:00) 5/3/2018 05/03/2018
Building Final Inspection Partial Pass 5/3/2018 (10:00 - 12:00) 5/3/2018 05/03/2018
Corrections:


Miscellaneous/Other
Comment Only
05/03/2018
Approved to stock, and train.

Miscellaneous/Other
Outstanding
05/03/2018
1) correct holes at passageway of the removed piping and such. 2) final needed by Environmental Health for the building final.

Building Final Inspection Partial Pass 5/9/2018 (8:00 - 10:00) 5/9/2018 05/09/2018
Corrections:


Miscellaneous/Other
Outstanding
05/09/2018
Bar and seating across does not provide for accessibility. The patio will have a table designated for accessibility, it needs to be labeled. The door floor set guide for the glass storefront doors needs to be transitioned due to the height, and requirements for access heights.

Miscellaneous/Other
Comment Only
05/09/2018
The access panel at 3rd floor shaft has been corrected, and the openings at the passageway. Approved

Building Final Inspection Failed 5/16/2018 (8:00 - 10:00) 5/16/2018 05/16/2018
Corrections:


Miscellaneous/Other
Comment Only
05/16/2018
The door guide/ transition at storefront still needs to be addressed further. Floor was floated and feathered to the bottom of transition but does not correct the height issue with the transition. Contractor will float and feather from transition back , at both sides to achieve compliance.

Building Final Inspection Partial Pass 5/18/2018 (8:00 - 10:00) 5/18/2018 05/18/2018
Corrections:


Miscellaneous/Other
Comment Only
05/18/2018
The area built up at storefront threshold appears to be code compliant. Contractor to complete the finish and feathering of edges for the next scheduled inspection

Building Final Inspection Passed 5/21/2018 (8:00 - 10:00) 5/21/2018 05/21/2018
Corrections:


Miscellaneous/Other
Comment Only
05/21/2018
Floor at the Transition has been floated to top of transition and feathered back in a ramp style. This meets the intent of the code. Final approved, ok to open to public.