Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 6/13/2018 (8:00 - 10:00) | 6/13/2018 | 06/13/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/13/2018
Wall framing approved to cover only. Ceiling framing was checked but cannot be covered till fir inspection and firestops are checked by building inspector.
|
||||
Framing Inspection | Partial Pass | 06/15/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/15/2018
Ceiling framing, firestops, and patched fireproofing approved. Ok to first layer ceiling with gypsum.... call for inspection before covering with second layer.
|
||||
Framing Inspection | Passed | 06/19/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/19/2018
First layer of gypsum at cieling approved, ok to install 2nd layer for this rated passageway.
|
||||
Building Final Inspection | Failed | 7/12/2018 (8:00 - 10:00) | 7/12/2018 | 07/12/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/12/2018
Mechanical permit required for the installation of approximately 57ft. Of ducting with 2 diffusers. Piping to be sealed at joints as well.
Call for inspection once permit is obtained.
|
||||
Building Final Inspection | Passed | 07/24/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/24/2018
Final approved, pending the fire inspection final.
|
||||
Fire Inspection Final | Passed | 07/24/2018 |