PRBD201800324
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 3/28/2018 (2:30 - 3:30) | 3/28/2018 | 04/11/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/28/2018
Not ready, trade inspections to be done prior to framing inspection.
|
||||
Miscellaneous/Other
Outstanding
04/11/2018
Bar area, framing non structural ceiling soffit completed, and visual of open to roof deck viewing insulated existing structure above ceiling. Provide all trade inspections prior to covering.
|
||||
Fire Inspection Final | Failed | 04/11/2018 | ||
Corrections:
Miscellaneous/Other
Carried Forward
04/11/2018
Need fire sprinkler permit by owner contractor Viking Fire Sprinkler, for above ceiling for women’s and men’s remodeled bathrooms and existing opened above ceiling for new bar area.
|
||||
Fire Inspection Final | Passed | 07/17/2018 | ||
Corrections:
Miscellaneous/Other
Outstanding
04/11/2018
Need fire sprinkler permit by owner contractor Viking Fire Sprinkler, for above ceiling for women’s and men’s remodeled bathrooms and existing opened above ceiling for new bar area.
|
||||
Building Final Inspection | Passed | 7/20/2018 (10:00 - 12:00) | 7/20/2018 | 07/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/20/2018
All work and inspections completed. E.H. Has also signed of with final.
|