PRBD201800537
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 2/20/2018 (10:00 - 12:00) | 2/20/2018 | 02/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/20/2018
Walls only approved to cover. Ceilings to have sprinkler and electrical inspection prior to the framing inspection.
|
||||
Framing Inspection | Passed w/ Conditions | 3/12/2018 (8:00 - 10:00) | 3/12/2018 | 03/12/2018 |
Corrections:
Miscellaneous/Other
Outstanding
03/12/2018
Gypsum Fire stop at grease duct to be rated for 2 hours. Contractor to add 2 more layers of gypsum , stuff flutes with mineral wool an apply fire caulking over the wool around the perimeter. The penetrations through the assembly will also need to be firestopped and metal collars installed to the ducting.
|
||||
Miscellaneous/Other
Comment Only
03/12/2018
Cloud ceiling approved for covering pending electrical and sprinkler inspections. Contractor to remove the brace that is attached to ducting.
Bathrooms and hallway ceilings approved for covering pending electrical and sprinkler inspections, contractor to add access panels to the 2 bathrooms for the shutoff valves.
Approval to cover is pending electrical and sprinkler inspections.
|
||||
Framing Inspection | Partial Pass | 3/29/2018 (10:00 - 12:00) | 3/29/2018 | 03/29/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/29/2018
Kitchen above ceiling approved pending the sprinkler inspection.
|
||||
Miscellaneous/Other
Outstanding
03/29/2018
Need to verify firestops to all floor drains, and 6” pvc piping below in kitchen and bar.
|
||||
Building Final Inspection | Passed | 04/20/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/20/2018
Final approved see issued permit for this project.
|