Permit Application Status

PRBD201800537


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201800537
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Framing only (no plan required per Duke) for Wahlburger's restaurant. Contractor wants to start work - EH approvals will be under separate building permit PRBD201800228 (application and plans still in the queue awaiting approval).
01/19/2018
01/19/2018
10/17/2018
04/20/2018

Locations

Permits

Permit Number: PRBD201800537

Building
Finaled
01/19/2018
10/17/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 2/20/2018 (10:00 - 12:00) 2/20/2018 02/20/2018
Corrections:


Miscellaneous/Other
Comment Only
02/20/2018
Walls only approved to cover. Ceilings to have sprinkler and electrical inspection prior to the framing inspection.

Framing Inspection Passed w/ Conditions 3/12/2018 (8:00 - 10:00) 3/12/2018 03/12/2018
Corrections:


Miscellaneous/Other
Outstanding
03/12/2018
Gypsum Fire stop at grease duct to be rated for 2 hours. Contractor to add 2 more layers of gypsum , stuff flutes with mineral wool an apply fire caulking over the wool around the perimeter. The penetrations through the assembly will also need to be firestopped and metal collars installed to the ducting.

Miscellaneous/Other
Comment Only
03/12/2018
Cloud ceiling approved for covering pending electrical and sprinkler inspections. Contractor to remove the brace that is attached to ducting. Bathrooms and hallway ceilings approved for covering pending electrical and sprinkler inspections, contractor to add access panels to the 2 bathrooms for the shutoff valves. Approval to cover is pending electrical and sprinkler inspections.

Framing Inspection Partial Pass 3/29/2018 (10:00 - 12:00) 3/29/2018 03/29/2018
Corrections:


Miscellaneous/Other
Comment Only
03/29/2018
Kitchen above ceiling approved pending the sprinkler inspection.

Miscellaneous/Other
Outstanding
03/29/2018
Need to verify firestops to all floor drains, and 6” pvc piping below in kitchen and bar.

Building Final Inspection Passed 04/20/2018
Corrections:


Miscellaneous/Other
Comment Only
04/20/2018
Final approved see issued permit for this project.