PRBD201800658
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 2/28/2018 (12:30 - 2:30) | 2/28/2018 | 02/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/28/2018
Wall framing of phase 1... approved to cover pending the scheduled plumbing inspection.
|
||||
Framing Inspection | Partial Pass | 4/6/2018 (2:30 - 3:30) | 4/6/2018 | 04/06/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/06/2018
Phase 2 walls approved. Leave the front wall open for electrical inspection.
Sprinkler inspection to be completed prior to above ceding building inspection. Some lighting to also be relocated, also call for that inspection before above ceiling building inspection.
|
||||
Building Final Inspection | Partial Pass | 4/13/2018 (10:00 - 12:00) | 4/13/2018 | 04/13/2018 |
Corrections:
Miscellaneous/Other
Outstanding
04/13/2018
3 offices and the break room can be turned over for tenant use pending the inspections and approval of electrical and fire inspectors.
|
||||
Building Final Inspection | Passed | 5/4/2018 (8:00 - 10:00) | 5/4/2018 | 05/04/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/04/2018
Final approved and pending the fire final.
|
||||
Fire Inspection Final | Passed | 5/4/2018 (8:00 - 10:00) | 5/4/2018 | 05/04/2018 |