PRBD201800778
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 3/9/2018 (10:00 - 12:00) | 3/9/2018 | 03/09/2018 |
Allowed extra time to get through Ikea. ajacobson 03/07/2018 3:43 PM | ||||
Corrections:
Miscellaneous/Other
Comment Only
03/09/2018
Framing at phase 1 set of bathrooms (restaurant group ) approved pending electrical inspection. No rough in plumbing inspection needed, all existing piping is remaining in place with new fixtures to be installed.
|
||||
Building Final Inspection | Partial Pass | 4/18/2018 (12:30 - 2:30) | 4/18/2018 | 04/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/18/2018
Phase 1 bathrooms, approved for final and public use.
|
||||
Framing Inspection | Passed | 5/7/2018 (8:00 - 10:00) | 5/7/2018 | 05/07/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/07/2018
Phase 2 bathrooms framing approved.
|
||||
Building Final Inspection | Failed | 6/6/2018 (12:30 - 2:30) | 6/6/2018 | 06/06/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
06/06/2018
1) lower hook at both ambulatory stalls to max 48”.
2) hand showers need to comply with accessibility, no gripping, grasping, flipping of wrist. Thes that are installed in men’s and women’s bathrooms do not comply.
|
||||
Fire Inspection Final | Failed | 6/6/2018 (12:30 - 2:30) | 6/6/2018 | 06/06/2018 |
Fire Inspection Final | Failed | 6/13/2018 (12:30 - 2:30) | 6/13/2018 | 06/13/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
06/13/2018
Need to close out and final sprinkler permit associateed with this scope of work
Need to test fire alarm system.
|
||||
Building Final Inspection | Failed | 6/13/2018 (12:30 - 2:30) | 6/13/2018 | 06/13/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
06/13/2018
1) lower hook at both ambulatory stalls to max 48”.
2) hand showers need to comply with accessibility, no gripping, grasping, flipping of wrist. Thes that are installed in men’s and women’s bathrooms do not comply.
|
||||
Miscellaneous/Other
Comment Only
06/13/2018
Inspection was canceled due to lack of testing for the sprinkler system/alarm system. Contractor to set up testing, and inspection and reset all inspections. The outstanding items that deal with accessibility need to be corrected and verified with final inspection.
|
||||
Fire Inspection Final | Passed | 6/15/2018 (8:00 - 10:00) | 6/15/2018 | 06/15/2018 |
Corrections:
Miscellaneous/Other
Outstanding
06/13/2018
Need to close out and final sprinkler permit associateed with this scope of work
Need to test fire alarm system.
|
||||
Building Final Inspection | Partial Pass | 6/15/2018 (8:00 - 10:00) | 6/15/2018 | 06/15/2018 |
Corrections:
Miscellaneous/Other
Resolved
06/15/2018
1) lower hook at both ambulatory stalls to max 48”.
2) hand showers need to comply with accessibility, no gripping, grasping, flipping of wrist. Thes that are installed in men’s and women’s bathrooms do not comply.
|
||||
Miscellaneous/Other
Outstanding
06/15/2018
Contractor needs to get the screw in levers that go the the hand shower raising control at slide bars. Install signage to all entry doors of bathrooms and changing rooms.
City of Bloomington will approve the use of these rooms with a follow up inspection to verify compliance.
|
||||
Building Final Inspection | Passed | 07/11/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/11/2018
All signage is installed and the levers that are to the hand shower height controls are now in place. This was all that needed to be completed for the final of this permit. Final approved.
|