Summary

PRBD201801643
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Remodel
Not Required
Tenant improvement of an existing 3016 SF retail space, architectural only. MEP is design build under a separate submittal by the general contractor.
02/26/2018
04/11/2018
06/02/2019
12/04/2018

Locations

Permits

Permit Number: PRBD201801643

Building
Finaled
04/11/2018
06/02/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 5/3/2018 (10:00 - 12:00) 5/3/2018 05/03/2018
Corrections:


Miscellaneous/Other
Outstanding
05/03/2018
The ceiling at store front along with the ducting is being supported off the mall bulkhead. As per mall and city requirements, the portion of ceilinghas to be independently supported, though it can attach at the bulkhead. 1) install support framing to independently support this framing. This section to be reinspected.

Miscellaneous/Other
Comment Only
05/03/2018
Approved to cover walls only at this time.

Framing Inspection Partial Pass 5/4/2018 (8:00 - 10:00) 5/4/2018 05/04/2018
Corrections:


Miscellaneous/Other
Comment Only
05/04/2018
Framing at storefront corrected and bracing added so ceiling is supported off the framing and not off bulkhead.

Above Ceiling Inspection Failed 5/25/2018 (10:00 - 12:00) 5/25/2018 05/25/2018
Corrections:


Miscellaneous/Other
Carried Forward
05/25/2018
1) Remove all cellophane and duct tape wrap around the ducts and the exposed insulation. 2) grease duct access panels to be protected with the 2hour wrap. Call for reinspection when completed.

Above Ceiling Inspection Failed 7/3/2018 (10:00 - 12:00) 7/3/2018 07/03/2018
Corrections:


Miscellaneous/Other
Carried Forward
07/03/2018
1) Remove all cellophane and duct tape wrap around the ducts and the exposed insulation. 2) grease duct access panels to be protected with the 2hour wrap. Call for reinspection when completed.

Miscellaneous/Other
Carried Forward
07/03/2018
Unable to view above ceiling, all tiles are in and there is no ladder onsite. To be reinspected with final inspection set up for 7/9/18.

Fire Inspection Final Not Ready 7/11/2018 (12:30 - 2:30) 7/11/2018 07/11/2018
Building Final Inspection Failed 7/11/2018 (12:30 - 2:30) 7/11/2018 07/11/2018
Corrections:


Miscellaneous/Other
Comment Only
07/11/2018
Contractor is not ready for inspection. He will reschedule inspection when ready.

Above Ceiling Inspection Passed 7/18/2018 (10:00 - 12:00) 7/18/2018 07/18/2018
Corrections:


Miscellaneous/Other
Resolved
07/18/2018
1) Remove all cellophane and duct tape wrap around the ducts and the exposed insulation. 2) grease duct access panels to be protected with the 2hour wrap. Call for reinspection when completed.

Miscellaneous/Other
Resolved
07/18/2018
Unable to view above ceiling, all tiles are in and there is no ladder onsite. To be reinspected with final inspection set up for 7/9/18.

Miscellaneous/Other
Comment Only
07/18/2018
Approved

Fire Inspection Final Passed 7/19/2018 (12:30 - 2:30) 7/19/2018 07/19/2018
Pending discussion with Kris and Jon about pending items in workflow. ajacobson 07/17/2018 9:24 AM
Building Final Inspection Partial Pass 7/19/2018 (12:30 - 2:30) 7/19/2018 07/19/2018
Pending discussion with Kris and Jon about pending items in workflow. ajacobson 07/17/2018 9:24 AM
Corrections:


Miscellaneous/Other
Outstanding
07/19/2018
1) as per E.H. Requirements clean space and clean floor and regroup the existing grout joints that are too low. 2) complete the necessary cleaning and fixes to the cooler

Miscellaneous/Other
Comment Only
07/19/2018
Approved to stock small wares only per E.H. And Building Inspector. Complete the items listed as “Outstanding “ and call for mechanical and fire inspection final as well as building and E.H. Final.

Building Final Inspection Partial Pass 12/4/2018 (12:30 - 2:30) 08/01/2018
Corrections:


Miscellaneous/Other
Comment Only
08/01/2018
As per Environmental Health, temp to open approved. Reinspection of health department items of correction to be done and inspected within 14 days.

Building Final Inspection Passed w/ Conditions 8/10/2018 (2:30 - 3:30) 8/10/2018 08/09/2018
Corrections:


Miscellaneous/Other
Comment Only
08/09/2018
Final approved pending E.H. Follow up for a couple minor corrections.

Framing Inspection Passed w/ Conditions 12/4/2018 (12:30 - 2:30) 12/4/2018 (PM) 12/04/2018
Corrections:


Miscellaneous/Other
Comment Only
12/04/2018
Framing approved pending the removal of wood in the framed towel dispenser opening. No wood allowed in storefront... this is a Mall Requirement. Send picture of removal and reframed or shimmed opening to inspector.