PRBD201801710
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Inspection Final | Pending | |||
| Building Final Inspection | Pending | |||
| Framing Inspection | Pending | |||
| Concrete Slab Inspection | Pending | |||
| Progress Inspection | Not Ready | 3/19/2018 (8:00 - 10:00) | 3/19/2018 | 03/19/2018 |
|
Corrections:
Miscellaneous/Other
Outstanding
03/19/2018
On site meeting - 9:00AM. NO ONE THERE. Went down stairs into underground ramp, no one there. Plumbing /building ? Space suite locked.
|
||||
| Framing Inspection | Partial Pass | 04/02/2018 | ||
|
Corrections:
Miscellaneous/Other
Outstanding
03/06/2018
Permit 2017 - 08157 was cancelled by contractor and city - contractor would not work with business representative. Permit cancelled by city.
|
||||
|
Miscellaneous/Other
Outstanding
03/06/2018
Framing - A. Interior Walls are not per plan for hallway accessibility for dimensions for push/pull door clearance required per plan. B. Second exit required by code using exterior ramp per drawings, but this does not have to be an entry.
|
||||
|
Miscellaneous/Other
Outstanding
04/02/2018
Framing - walls only. Call for above ceiling framing for 1 hour separation walls above ceiling.
|
||||
| Concrete Slab Inspection | Failed | 01/03/2019 | ||
| Exterior sidewalk - vs ramp. Slope greater than 1: 12 to be classified as a sidewalk, not a ramp. Other option - if classified as a ramp a maximum rise of less than 30 inches is allowed at a slope not greater than 1:12 = 8.33%. Handrail required for ramp if in the path of egress. Concrete sidewalk poured by contractor, fall 2018. No pre pour form inspections requested. | ||||
| Framing Inspection | Partial Pass | 3/5/2018 (10:00 - 12:00) | 3/5/2018 | 01/03/2019 |
| Main floor level of existing building. A. Framing for above ceiling gypsum rating of new one hour separation, to the existing building main floor corridor. Location of tenant - North end of building off elevators. B. New tenant Fardosa for daycare is now running state MN licensed autism learning center, and Space is sprinklered. B. Need fire final. C. Temp occupancy given, conditional on fire marshal sprinkler final. D. Environmental health - food licensed was planned and applied for the catering in of meals. Business is no longer a day care, and is licensed with the state for an autism learning center. Parents prep and pack individual special dietary lunches for each child. | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
03/06/2018
Permit 2017 - 08157 was cancelled by contractor and city - contractor would not work with business representative. Permit cancelled by city.
|
||||
|
Miscellaneous/Other
Carried Forward
03/06/2018
Framing - A. Interior Walls are not per plan for hallway accessibility for dimensions for push/pull door clearance required per plan. B. Second exit required by code using exterior ramp per drawings, but this does not have to be an entry.
|
||||