PRBD201801861
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 4/2/2018 (8:00 - 10:00) | 4/2/2018 | 04/02/2018 |
Corrections:
Miscellaneous/Other
Outstanding
04/02/2018
Wall framing in the bathroom groups approved to cover pending electrical inspection approval.
|
||||
Above Ceiling Inspection | Passed w/ Conditions | 4/19/2018 (10:00 - 12:00) | 4/19/2018 | 04/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2018
Above ceiling approved to all bathrooms groups under this scope of work.
|
||||
Miscellaneous/Other
Outstanding
04/19/2018
Resupport the ceilings in the 2 bathroom group by means of added framing. The ceiling cannot be supported off the ductwork.
This will be checked at final inspection.
|
||||
Fire Inspection Final | Passed | 4/23/2018 (8:00 - 10:00) | 4/23/2018 | 04/23/2018 |
Building Final Inspection | Passed | 4/23/2018 (8:00 - 10:00) | 4/23/2018 | 04/23/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/23/2018
Final approved.
|