PRBD201801959
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Failed | 4/6/2018 (8:00 - 10:00) | 4/6/2018 | 04/06/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
04/06/2018
Need electrical and plumbing rough in approvals. Provide city approved plans on job site showing corridor revisions.
|
||||
Framing Inspection | Passed w/ Conditions | 4/11/2018 (8:00 - 10:00) | 4/11/2018 | 04/11/2018 |
Corrections:
Miscellaneous/Other
Outstanding
04/06/2018
Need electrical and plumbing rough in approvals. Provide city approved plans on job site showing corridor revisions.
|
||||
Miscellaneous/Other
Outstanding
04/11/2018
Framing - A. Framing approved with electrical and plumbing rough in approval. B. Corridor wall to be 1 layer each side, to deck above and tight around ductwork, to be inspected on final with tiles removed both sides and fire caulked. C. Fireproofing on existing steel - approved. D. Firecaulking for plumbing at floor - approved.
E. PRINT CITY APPROVED DRAWINGS FOR JOBSITE FOR FINAL INSPECTION.
|
||||
Fire Rating Inspection | Passed | 04/11/2018 | ||
Fire proofing at existing steel beams. OK. Firecaulking for plumbing floor penetrations. OK. | ||||
Corrections:
Miscellaneous/Other
Resolved
04/11/2018
Fire proofing steel beams existing and plumbing floor penetrations.
|
||||
Fire Inspection Final | Passed w/ Conditions | 4/27/2018 (8:00 - 10:00) | 4/27/2018 | 04/27/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/27/2018
Approved, pending Building Final Inspection
|
||||
Building Final Inspection | Passed | 4/27/2018 (8:00 - 10:00) | 4/27/2018 | 04/27/2018 |
Corrections:
Miscellaneous/Other
Outstanding
04/27/2018
Final - approved, contingent upon final electrical 10 day temp. for cubicals
|