PRBD201802044
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed w/ Conditions | 4/27/2018 (12:30 - 2:30) | 4/27/2018 | 04/27/2018 |
Corrections:
Miscellaneous/Other
Outstanding
04/27/2018
Framing - A. DROP STEEL STUD SOFFIT. Add screws missing on the inside of all vertical studs hanging from ceiling track radius. Add screws top and bottom of all studs. B. Building maintenance on site and wants access panel to HVAC supply dampers after sheetrock. Open dampers for now as discussed. C. ELECTRICAL - REQUIRES ABOVE CEILING inspection for temp control wiring, and lighting, FIRE INSPECTOR requires above ceiling for sprinkler. D. Exit signage and 90 minute minimum emergency lighting required.
|
||||
Fire Inspection Final | Passed | 5/25/2018 (8:00 - 10:00) | 5/25/2018 | 05/25/2018 |
SAC determination pending. No final inspection until SAC determination has been received and paid. Morehouse Michael 03/29/2018 7:16 AM | ||||
Building Final Inspection | Passed | 5/25/2018 (8:00 - 10:00) | 5/25/2018 | 05/25/2018 |
SAC determination pending. No final inspection until SAC determination has been received and paid. Morehouse Michael 03/29/2018 7:16 AM |